Winter Service Policy 2023-24

Introduction

East Dunbartonshire Council (The Council) as Roads Authority has a statutory obligation under the provisions of Section 34 of the Roads (Scotland) Act 1984, to take such steps as it considers reasonable to prevent snow and ice or indeed the consequences of any other weather condition endangering the safe passage of vehicular and pedestrian traffic over the Council’s public roads.

The intention of this duty is not that the council will take immediate and simultaneous steps to clear/treat every road whenever ice formations or snow accumulations, floods, fallen trees or other impediments exist. To do so would be impossible and beyond the limit of the resources available and, indeed, this is recognised by the Courts.

To assist authorities in prioritising the treatment of their network the UK Liaison Group (UKLG), made up of senior professionals, key stakeholders and industry experts, have developed the Well Managed Highway Infrastructure Code of Practise.

Instead of providing specific guidance and recommendations, the code provides overarching principles, which must be considered by each authority in the development of their winter service. Through analysis of local strategies and objectives, a winter service can be developed which will better meet the specific needs of their authority.

Winter Service deals with regular, frequent and reasonably predictable occurrences like low temperatures, ice and snow, as well as with exceptional events. Whilst the effects of climate change are likely to result in an increased frequency and intensity of severe winter events, these can be taken into account in Winter Service planning. Therefore, Winter Service can and should be subject to the same regime of planning, delivering, reviewing and improving as other aspects of the roads’ maintenance regime.

The Council therefore prepares a plan of action, setting out how it intends to treat ice and snow in a reasonable and logical manner. In order to deal efficiently and effectively with Winter Service delivery, operations need to be planned in a systematic manner and it is essential that a policy and procedures, with clearly defined priorities, is established. The objective is to provide a Winter Service that will permit the safe movement of all road users, including pedestrians, whilst minimising effects on the environment and the consequences of adverse weather conditions to the national and local economy and all related influences on inhabitants of the country.

The purpose of the Council’s Winter Service Policy is to set out the operational parameters and procedures that will ensure that the statutory obligations are achieved. 

This policy is for the adopted public road network only. All other Council-owned land and properties would be subject to the treatment procedures of the relevant responsible Service departments.

On this page you will find information on:

 

  1. Policy Objectives 
    1. Customer Service 
    2. Safety
    3. Serviceability 
    4. Sustainability 
       
  2. Operational Arrangements & Procedures 
  1. Winter Period 
  2. Coordination and Collaboration 
  3. Pre-Winter Preparation 
  1. Communications 
  1. Information to the public 
  2. Routine Information During the Winter Period 
  3. Severe or Prolonged Winter Communications
  1. Meteorological Forecasts & Decision Making Process 
  1. Road Sensors
  2. 36 Hour Forecast 
  3. Two to Ten Day Forecast 
  4. Combined Roles of MG and Duty Officer 
  5. Specific Conditions Considerations 
  1. Treatment Routes 
  1. Carriageways 
  2. Footways
  3. Cycle Routes 
  4. Grit Bins 
  5. Car Parks 
  6. Response and Treatment Times
  7. Other Council Owned Locations 
  1. Resilience 
  2. Contingency Planning for Severe Weather or Resource Shortages 
  1. Severe Weather and Salt Shortages 
  2. Pandemic Resilience 
     
    1. Assistance by Others 
    2.  Hierarchy of Treatments 
    3. Road Closures
  1. Arrangements for Ploughing and Continuous Gritting
  1. Public Holidays
  2. Additional Resources 
  3. Plant
  4. Warning Signs 
  5. Salt 
  1. Severe Wet Weather and Flooding 
  2. Operational Reporting & Retention of Records
  3. Post Snow Clearance and Maintenance
  4. Annual Review

Appendix A – Current Arrangements with Adjacent Councils 
Appendix B – Plant and Transport 
Appendix C – Spread Rate Chart 
Appendix D – Vehicle Weights and Capacities 
Appendix E – Grit Bin Application Criteria 

 

  1. Policy Objectives

    It is the aim of East Dunbartonshire Council to provide an efficient and effective Winter Service within the resources available, which meets the core objectives set out in the Well Managed Highway Infrastructure Code of Practise 2016 as well as Council strategies for transport, accessibility and network management.

    The Winter Service will also contribute to wider Council strategic values and objectives for excellent customer service, safety of road users and employees, serviceability of the road network and sustainability. 
    1. Customer Service 
      User needs and expectations are, and continue to be, a significant influence in determining the response to winter conditions, which allow the safe movement of pedestrian and vehicular traffic appropriate to the prevailing weather conditions. It is important to continually communicate with our customers and provide clear guidance and information on both on our current treatment and levels of service.

      This Policy seeks to ensure a customer focused approach and to deliver customer satisfaction through demonstrating an efficient, effective and proportionate response to winter conditions.
       
    2. Safety
      Complying with statutory obligations and meeting road users’ needs for safety are vitally important to the successful delivery of the winter service. 

      As well as the safety of the public, using the network winter service operations will be conducted with due regard to the provisions of the Health and Safety and Work Act 1974. Treatment plans, actions and working patterns will be designed to ensure the Council provide the required and proportionate response to weather conditions and keep delays, diversions and road closures to a minimum during adverse 
      weather.
       
    3. Serviceability 
      Maintaining availability and reliability of the road network is a key objective for Winter Service and one where user judgments of performance will be immediate rather than longer term. The service standards for Winter Service define the Overall Winter Period, the Core Winter Period, and the desired level of resilience and treatment routes.
       
    4. Sustainability 
      Low temperatures and the formation of ice can cause serious damage to the fabric of running surfaces and accelerated damage of the network. Effective  Winter Service can contribute to a reduction in whole life costs and minimise damage to the environment.
       
  2. Operational Arrangements & Procedures 
    The following section details the operational arrangements and procedures in delivering the Winter Service Policy.
  1. Winter Period 
    The principal Winter Maintenance period covered will extend from midnight Thursday 12 October 2023 to the morning of Thursday 18 April 2024. However, cover will be available, at short notice, out with this period, should weather conditions dictate
     
  2. Coordination and Collaboration 
    Before the onset of the winter period, the Winter Maintenance Team will liaise with adjacent authorities to co-operate and co-ordinate response, including establishing contact points for winter service operations and to determine the arrangements for the treatment of shared routes, including response, and treatment times. Such existing arrangements are tabled in Appendix A.

    East Dunbartonshire Council is a member of the West of Scotland Local Authority (WoSLA) Weather Forecast Partnership with 12 other local authorities. In addition to providing a forum to discuss best practice and collaboration opportunities, the Partnership worked together to secure the services of a meteorological forecast supplier. By working together, we can ensure best value is obtained through the contract.

    Other collaborative arrangements such as shared services, lead authority arrangements, collaborative service procurement, and sharing depots and salt stock and determining common treatment policies will be subject to ongoing review to provide an effective and value for money approach to increasing winter service resilience. Collaborative working arrangements are coordinated both at area and at national levels, through the activation of the Strathclyde Emergencies Coordination Group (SECG) and the Scottish Government Resilience Room (SGoRR) respectively as may be required by specific circumstances at any given time. In addition, salt stock levels for all local authorities are monitored through the national Salt Monitoring Database. This national approach ensures any resource issues are highlighted as early as possible and the sharing of available salt can be arranged quickly is response to shortages and severe weather events.
     
  3. Pre-Winter Preparation 
    Over the course of the summer period, the Winter Maintenance team will meet to review the performance over the previous winter and discuss any lessons learned. An action plan will be developed and these issues addressed ahead prior to the following winter period and the Winter Service Policy updated to reflect these changes.

    As the new winter season, approaches the Winter Team will liaise with Fleet Services. Fleet Services will carry out pre-winter checks on all vehicles and plant required for Winter Service treatment and snow clearance. This check will include the calibration of the gritting controls.

    In addition, the Winter Maintenance Team’s training and vocational qualifications and records are reviewed, and the relevant measures taken to ensure the appropriate level of competence is available and that all relevant health and safety procedures are in place prior to the onset of the Winter Service season.

    Salt will be purchased prior to the onset of winter and delivered to Broomhill Depot to ensure stocks are at appropriate levels throughout the winter period and will be restocked as necessary.

    At the beginning of the overall winter period in early October, a full-scale trial of the Winter Service Policy will take place. This trial will include the driving of all specified primary routes, the fitting of snowploughs to vehicles, the setting of the controls to vary the rate of spread. The Winter Service Management Team will coordinate and control the trial and take the necessary actions to address any problems encountered prior to the start of the winter period.
  1. Communications 
  1. Information to the public 
    The Winter Service Plan has taken into account the need for procedures to ensure effective communication of information for the public before and during both normal and severe winter conditions. Communication and publicity with the wider public and community will promote understanding and involvement in winter maintenance. This provides opportunities and challenges, which will be positively addressed and provide an important opportunity to demonstrate understanding of users’ needs, and a strong service commitment.

    It is of crucial importance that the Winter Service Policy and standards within it are widely available and understood by users and the community. As far as possible, network users will be made familiar with treatment routes, particularly in severe weather conditions via the web and social media. Additional and more frequent information will be supplied during periods of severe weather in line with the Council’s Severe Weather Communication and Escalation protocols. This will help in ensuring that expectations are realistic and consistent with the resources available as well as maintaining public safety.

    Public awareness will be addressed by making available a copy of the complete Winter Service Policy including winter maintenance routes and grit bin locations. In addition to this, should any member of the public make enquiries to the content of the plan, the relevant information will be provided in a manner which suits. As an alternative to the full version, a non-technical summary of the Winter Service Plan will be widely available for users and the community including a brief summary of the treated network, together with guidance on safe use of the network. Information will be reviewed annually and made available through the web site.

    Over the course of the Winter Period, the Roads Network team will actively seek to improve the volume and nature of the information made available to the public through social media and via the Council website. This includes investigating the use of live tracking of the gritting vehicles on the Council’s website

    Full copies of this Winter Service Plan are made available to Elected Members and members of the Senior Management Team, Communications team and other external organisations.
     
  2. Routine Information During the Winter Period 
    During the winter period, the Duty Officer will coordinate the daily communication of information for the public. The Council website will be updated daily and regular social media posts will be published on Facebook and Twitter to provide position statements of decisions taken, planned actions and operational responses. This will allow for continuity of service to be monitored, actions taken where it is considered appropriate and will help in ensuring that expectations are realistic and consistent with the resources available as well as maintaining public safety.

    The Duty Officer will liaise directly with colleagues in the Customer Service and Communications teams during severe conditions who will be provided with updates on the actions and operational responses to allow the members of the public to be informed as best as possible. When there are forecasts of more serious weather, the communications will be increased as deemed necessary and relevant.

    The Winter Service Management Team will establish effective working arrangements with local media via the Communications team to enable the presentation of timely and accurate information and advice on network condition and use, network availability and risk of severe conditions such as snow and black ice as it is required.
     
  3. Severe or Prolonged Winter Communications
    During severe or prolonged winter events, the routine communications will continue as normal, however in addition to this, the Council has developed a Severe Weather Communication and Escalation Protocol.

    The Duty Officer and Winter Service Management Team will liaise directly with the Communications team, Customer Service team and the Corporate Contingencies team in conjunction with Organisational Transformation team and Depute Chief Executive to coordinate and facilitate the communication to the wider public.

    This communication may include press, local radio or other broadcast media to enable the presentation of timely and accurate information and advice on network condition and use, including travel information, network availability and risk of severe conditions such as snow and black ice.

    Briefing notes will be prepared and issued to Senior Managers and Elected Members to provide the necessary position statements and actions taken during the severe or prolonged conditions.

    As part of this Severe Weather process Senior Management, along with the Winter Maintenance Team will liaise with NHS, emergency services and the Health and Social Care Partnership to arrange for any necessary access to particularly vulnerable residents, such as those in need of medical treatment or outpatient care.
  1. Meteorological Forecasts & Decision Making Process 

    The meteorological forecasts and road warnings will be provided by Met desk.
    The following tools are used to assist in the preparation of the weather forecasts:
  1. Road Sensors
    The Council has installed three road condition sensor stations at strategic points throughout the area.
    The sensors give a variety of information relating to actual road conditions such as:
  • Road condition, i.e., wet, dry, frost or snow
  • Residual salt
  • Road surface temperature

The location of the stations are:

  • Strathblane Road at Haughhead, Lennoxtown
  • Kilsyth Road at Shirva Road, Kirkintilloch
  • Baljaffray Road, Bearsden

The information received from the stations is transmitted to Met desk to be used in conjunction with other meteorological data collected separately to predict the weather conditions throughout the area.

  1. 36 Hour Forecast 
    Each day throughout the Winter Service period, Met desk shall prepare and transfer, via the Web, a 36- hour text forecast at the following times:
  • 0600 hours
  • 1200 hours
  • 1800 hours

This text forecast shall cover the following 36-hour period. The forecast shall also include a 36-hour table showing forecast minimum road surface temperature each hour, times between which the road surface temperature will be at or below zero degree Celsius, comments on weather conditions and weather hazards likely to affect road conditions and start and end times of precipitation.

  1. Two to Ten Day Forecast 
    A two to ten day text forecast covering a general geographical area of East Dunbartonshire will be issued by the Met desk on a daily basis
     
  2. Combined Roles of MG and Duty Officer 
    The Council will take full advantage of decision support systems and services to enable timely, efficient and accurate decision-making. Decision support systems and management information, together with local experience, are the basis of effective Winter Service delivery. Decision support information will be used by the authority’s designated Winter Service Duty Officer in deciding the appropriate course of action that is required.

    In order to enable the Duty Officer to decide on the appropriate course of action, there will be unlimited 24-hour direct access to the Duty Forecasters at MG throughout the winter period.

    During periods of adverse forecasts and where there is uncertainty about course of action required as a result of the forecast update, consultation should take place with trained and experienced members of staff and/or the Duty Forecaster at MG. Warning of heavy snow, heavy rain or severe gales will be issued whenever any of these are likely to cause widespread disruption to traffic on the road network. The Duty Forecaster at MG will, in the first instance, make contact with the ‘on call’ Duty Officer to advise of the warning. The Duty Officer will then refer to the Council’s weather forecast web page for a textual update of the warning. The Duty Officer will arrange the appropriate response to the   predicted weather conditions.

    Non-routine updates shall be prepared by the Duty Forecaster at MG before midnight whenever necessary. The Duty Forecaster shall telephone the Duty Officer two hours prior to the onset of changed conditions and follow-up with a non-routine updates to the Council’s web page. The Duty Officer will arrange for the appropriate response to the predicted weather conditions.
     
  3. Specific Conditions Considerations 
    If freezing conditions are forecast or are expected after, rain then salting operations will be delayed as long as possible to minimise the chance of the loss of salt through possible run-off. 

    If freezing conditions coincide with rain then salting operations will commence as soon as practical and will continue until all primary routes are free of icy conditions.

    In marginal conditions when the weather forecast does not indicate icy conditions, but the temperature is expected to fall below +1oC the patrol route will be carefully monitored by the patrol team. If significant areas of ice are identified, the patrol will commence treatment immediately and initiate callout arrangements. In such circumstances, it may be necessary to deploy a patrol to monitor certain roads and weather conditions. The patrol will assess road conditions and salt the patrol route as instructed covering areas of seepage and known wet spots within the route see Table (A).

    Table (A) – Spread Rates
    Road Status Rate of dry salt spread
    Mainly dry, some wet patches 10g/m2 to wet patches only
    Formation of hoar frost expected 10g/m2 to 15g/m2
    Roads wet 10g/m2 to 15g/m2
    Ice already forming 20g/m2 to 40g/m2

    Subject to forecasters decision

  1. Treatment Routes 

    Detailed route planning for each aspect of Winter Service has been optimised to ensure economic, efficient and effective resource allocation. The operational and financial resources available for the Winter Service are limited and accordingly it is necessary to prioritise the treatment of both the carriageways and footways that make up the public road network. These priorities are shown in sections 6.1 and 6.2 below.
  1. Carriageways 
    Each of the carriageways in our network will be evaluated in line with the WMHI Code of Practise along with key strategic objectives to categories our treatment routes into four categories
  • Primary Routes
  • Secondary Routes
  • Patrol Routes
  • Minimum Winter Network

Primary Routes
Our primary routes will be assessed prioritised against our hierarchy of inspection (as shown in table B) and locations of importance such as:

  • Access to Fire and Rescue, Police and Ambulance and medical centres
  • Public transport routes and access to stations, garages and depots
  • Access to main industrial and commercial centres of key importance to the local economy
  • Access to remote and rural areas
  • Known problems areas such as steep gradients and flooding issues
  • At least one access to local schools

It is recognised that it may not be possible to treat all bus routes, shopping areas or medical centres as part of precautionary routes; however, such locations will be prioritised in any secondary operations.

It is intended, as far as is reasonably practicable, that during precautionary salting all primary routes will be treated before the start of the morning peak, i.e. before 07.30 hrs.

Table (B) - Hierarchy of Inspection

Carriageway
Category
Hierarchy
Description
Type of Road General
Description
Description
1 Motorway N/A N/A
2 Strategic Route Principal A Roads
between Primary
Destinations
Routes for fast moving or long distance traffic
with varied frontage access or pedestrian
traffic. Speed limits generally in excess of
40mph with few junctions.
3a Main Distributor Major Urban Network &
Inter-Primary Links. Short
to medium distance
traffic.
Routes between strategic routes and linking
urban centres to the strategic network with
limited frontage access. In urban areas speed
limits are usually 40mph or less.
3b Secondary
Distributor
Classified Roads (B & C
Class) and unclassified
urban bus routes carrying
local traffic with frontage
access and frequent
junctions.
In rural areas these roads link the larger
villages and HGV generators to the Strategic
and Main Distributor Network. In built up areas
these roads have 30mph speed limits and
high pedestrian activity.
4a Link Road Roads linking between
the Main & Secondary
Distributor Network with
frontage access and
frequent junctions.
In rural areas these roads link the smaller
villages to the distributor roads. They are
of varying width and not always suitable of
carrying two-way traffic. In urban roads they
are residential or industrial inter connecting
roads with 30mph speed limit.
4b Local Access
Road
Roads serving limited
numbers of properties
carrying only access
traffic.
In rural areas these roads serve small
settlements and provide access to
individual properties and land. They are
often single lane and unsuitable for HGV. In
residential areas they are residential loop
roads or cul-de-sacs.

Secondary Routes
The remainder of the network may only be treated during prolonged periods of adverse weather of ice and snow to the extent that weather conditions permit available resources to be allocated to these other roads and that the treatment of the secondary routes would not be detrimental to the level of service of the primary routes. Treatment of the remainder of the network may take several days from the onset of prolonged severe weather or longer in exceptional circumstances. (See section 8 for further information.)

Patrol Route
When the weather forecaster only predicts icy conditions above certain heights, or in certain localities, then only the roads at these locations will be treated. It should be noted that in these circumstances the actual conditions of the road network within the patrol route will be monitored by the patrol and, if necessary, additional resources will be deployed.

Minimum Winter Resilience Routes
During prolonged periods of extreme or prolonged weather conditions or when resources or salt balances can be effected it may be necessary to concentrate only on essential treatment routes. These routes will include roads of key strategic importance. 

The table below provides a basic breakdown of category for clarification.

Table (C) – Carriageways

Category Type Description / Comment
Primary Network Routes Strategic Routes, Main
& secondary Distributor
Roads & Link Roads
Roads which essentially link the centres of
population and commercial activity

At least one access to each school will be
included in this category.

Roads which distribute traffic within a district
and link the Main Distributor Roads with the
General Access

Roads.

At least one road into each residential area
as well as roads that has steep gradients or
tight bends.
Secondary Network
Routes
Minor link roads, local
Access Roads Public
Car Parks
Roads which provide access to residential,
industrial areas and cul-de-sacs etc.
Minimum Winter Network
Routes
Strategic Routes,
Main and Secondary
Distributor Roads
Roads which essentially link the centre of
population and commercial activity (During
extreme conditions only).

Table (D) – Snow Conditions

Snow Conditions Salting Network Other Routes
Slight, expected less than 25mm Presalt at 10g/m2 No action
Moderate, expected 25 – 100mm Presalt at 20g/m2, when snow
depth is over 50mm and treat as
described in parts (3 to 9) below
When plant is available, treat as
per salting network. Grit when
snow is hard packed.
Heavy, expected greater than
100mm
Presalt at 20 to 40g/m2. Plough
when snow depth is over 50mm
and treat as described in parts (3
to 9) below
When plant is available, treat as
salting network. Grit when snow
is hard packed.

Subject to forecasters decision

On receiving a snow warning, the following procedure should be carried out:

  1. Fix ploughs to all vehicles if significant accumulations or drifting are expected.
  2. Pre-treat the spreading network in accordance with Table (C) above immediately prior to snow falling to prevent snow setting on the road surface.
  3. Start ploughing as soon as snow becomes deep enough to plough, i.e. approximately 50mm in depth.
  4. After ploughing, treat un-compacted snow with salt at 10 g/m2 per 25mm depth of snow and replough to remove slush.
  5. When prolonged falls are forecast it will be found useful to continuously plough from the onset of snow to prevent build up and to prevent compaction by traffic. Such ploughing can be combined with simultaneous salting at 20-40 g/m2 so that a wet base is maintained. However, once snow depths of 120 mm have been reached, or when tackling snowdrifts or where vehicles are operating on gradients, it may be desirable to continue ploughing without salting. The weight of a salt load will aid vehicle traction when ploughing.
  6. After ploughing, a further treatment of salt is required at the rate of 10 g/m2 for every 25 mm depth of un-compacted snow for each degree centigrade that the  surface temperature is below freezing (see 8 below). As snow melts under the action of salt, keep ploughing to remove slush.
  7. If snow has become compacted and the temperature is low (-5oC or below) neat salt must not be used, as it will accumulate in the form of salt solution in depressions and produce a very uneven and slippery running surface. In these circumstances, spreading of grit is advised.
  8. A 50/50 grit/salt mix can be used on hard-packed snow. Grit is not required on un-compacted snow, as the action of salt will cause the snow to melt allowing the slush to be removed easily by ploughs.
  9. Very low temperatures do not usually follow immediately after a snowfall and it is therefore very important to apply salt early, plough early, salt again and get the resultant slush off the road before compaction by traffic.
  1. Footways
    When it is determined that it is necessary to treat the footway network, all primary footways will be treated before 08.30 hrs, as far as is reasonably practicable and subject to prevailing weather conditions and available resources. Footways and footpaths tend to retain more residual deposits of road salt and therefore it is not always necessary to treat them every time there is a prediction of the onset of freezing conditions. However, on each occasion, an assessment will be made of the level of residual salt and when appropriate the necessary treatment will be carried out.

    The treatment of footways and footpaths may have to be locally curtailed, due to obstructions caused by wheelie-bins, on collection days. This situation will be most acute where mini-tractor equipment is used to treat footways. Due to the random nature of this eventuality the Council will only return once the wheelie-bins have been removed from the footways to carry out the required treatment.

    Primary footways, as detailed in Table (E) below, are primarily town centres and pedestrian precincts and footways adjacent to main facilities or at busy thoroughfares within the urban environment. This is in contrast to the primary routes for carriageways, detailed in Table (C and D), which tend to be roads that essentially link the centres of population and distribute traffic within the district.

    Table (E) – Footways
    Category Type Description / Comment
    Primary Main Shopping Areas Footways in town centres,
    pedestrian precincts and
    designated routes to schools.
    Secondary Busy Urban Areas Footways adjacent to community
    centres, main facilities / busiest
    locations used by the elderly,
    health centres, schools. Also
    footways where physical
    features such as steep gradients
    or drainage problems create
    enhanced risks.
    Other Less used Urban Footways and
    Rural Footways
    These will only be treated as
    resources permit


    Notes on the interpretation of the Policy for Footways and Footpaths

  1. Within any Priority, categories of footway/footpath will be suspended from treatment in reverse order if, and for as long as conditions so dictate and whilst the principal routes are being dealt with. Every effort will be made to avoid this eventuality. 
  2. On occasions, during adverse weather conditions, only the highest of higher priority routes will be treated. There may be times when only Priority F1A routes and the most important pedestrian links, within the F1B list, will be treated.
  3. In snow conditions it is imperative that an early start is made to prevent hard packing by pedestrians. Authorisation, by the Duty Manager, for salt and/or grit will be required if packing occurs. Easily accessed sources of grit may have to be established.
  4. In pedestrian areas, where gritting equipment can take access, it should do so with due care.
  5. Pedestrian areas, within shopping centres, which gritting equipment cannot reach or where street furniture screens part of the footway, only 2m widths, outside each frontage and limited crisscrossing tracks will receive treatment.
  6. Notwithstanding the descriptions given within each Priority, a footway route would usually be provided in preference to that of a footpath, even though it may be of greater length.
  7. The connecting footway must be used, by the public, on a regular and predicable basis. Public buildings are those providing a primary and intensive service to the public during the majority of the day. This would include hospitals, health centres, police stations, libraries, local authority offices and post offices.
  1. Cycle Routes 
    Cycle routes are considered to include cycle lanes on carriageways, cycle route adjacent to carriageways on carriageway provision with cycle symbols and shared use facilities. It is recognised that there are specific risks associated with the use of bicycles over the winter period.

    Whilst it will not be possible to include all designated cycle routes within our primary treatments, particularly any remote from the carriageway each location on the public road network will be examined and assessed for possible inclusion. Where it is not possible to treat designated cycle routes it is important that alternative treated parts of the road network be available.

    Special provision will be given for the treatment of any segregated cycle route where treatment of the adjacent carriageway is unlikely to provide any de-icing.
     
  2. Grit Bins 
    At locations which are not currently on primary routes or at strategic locations where there are known issues; such as gradients and sharp bends, grit bins will be placed and provided for use by the public. These bins will be regularly serviced throughout the winter and will remain at these locations as far as reasonably practicable. In extreme conditions or when there is the need to conserve salt stock levels, grit bins may require to be stocked using either a salt-sand mix or in some occasions sharp sand only, as detailed in section 3.8.

    In addition to the grit bins which are strategically placed throughout East Dunbartonshire, members of the public may also uplift small quantities of grit (up to 50kg) free of charge from Broomhill Depot, Broomhill Industrial Estate, Kilsyth Road, Kirkintilloch, G66 1TF and Langfaulds Cemetery, Baljaffray Road, Bearsden, G61 4PU.

    Local businesses will not be permitted to uplift grit from these locations.

    Requests for bins will be assessed on a case-by-case basis. Should residents feel that a grit bin is required in a specific location one can be requested via the Council’s Website. All requests will be evaluated against the criteria shown in Appendix E and included in the application form and installed if there is free resource is available.
  3. Car Parks 
    The Council is responsible for the maintenance of a number of public car parks across the area. Whilst it would not be practical to treat all of these locations whenever inclement weather is predicted, these locations will be treated on a priority basis dependant on level of use, weather forecasts and availability of resources.

    The duty officer will liaise with Streetscene team members regarding programmed treatment plans and weather forecasts each day over the winter period and to allow decision makers within the service to direct resources to these areas when required.

    Priority will be given to the treatment of car parks which service key strategic transport hubs across the authority. The treatment of any additional car park locations will be prioritised based on expected level of use, predicted weather forecast and availability of additional resources.
     
  4. Response and Treatment Times
    The response time, which is defined as the period between decisions being taken to begin treatment and vehicles leaving the depot, is targeted at no more than one-and-a-half hours. This applies both within and outside normal working hours; however, this could be exceeded given the prevailing weather conditions and availability of resources.

    Treatment times, which is defined as the period between vehicles leaving the depot and the completion of treatment on all priority routes, is adopted based on risk assessment of local circumstances that provide for the completion of pre-treatment before ice forming. It should, however, be recognised that treatment times might vary in different weather conditions although this time should not exceed three hours in normal circumstances.
     
  5. Other Council Owned Locations 
    The information contained within this treatment plan is for the treatment of the public road network only. Treatment of other Council-owned areas will be dictated by the individual plans for the service responsible. however the Duty Officer will liaise with those departments regarding the expected weather forecast where required.
  1. Resilience 
    This plan considers - and has adopted - local service standards for resilience of the Winter Service in terms of the number of days continuous severe conditions salting on a defined Minimum Winter Network throughout the Overall Winter Period.

    The Code of Practice suggests resilience levels should be established to provide six days resilience for salt and other resources, including equipment, drivers and fuel. The Council’s desired minimum stock level for salt will however be based on 12 days resilience as per Table (F) below. This approach is based on the ability to deliver a defined winter service should the Council hold or have guaranteed access to sufficient salt, gritting vehicles and drivers and other essential resources to deal with severe winter weather conditions.

    In addition, salt levels across all local authorities are monitored nationally through Traffic Scotland Salt Level Monitoring database. Each authority must update the current balance and usage each week to ensure suitable salt levels are being maintained and to provide an opportunity for any sharing of resources in severe weather events.

    To provide additional resilience within the Roads Network Team drivers, the use of route guidance has also been introduced. This will ensure accuracy and consistency within the treatment of each route should additional resources be required to assist with the treatment of the carriageway network.

    Table (F): Resilience Standards
    - Carriageway
    Routes
    Footway Routes Grit-Bins Totals
    Routes 1 to 8 1 to 11 515  
    Categories Primary Primary &
    Secondary
    All  
    At 20g/m2 80T 12T 110T  
    Frequency 3 actions per 24
    hour period
    1 action per 24
    hour period
    1 action per 72
    hour period
     
    Minimum
    Resilience Period
    12 days 12 days 12 days  
    Total Usage 2880T 144T 330T 3354T


     

  2. Contingency Planning for Severe Weather or Resource Shortages 

    It is important for all service planning that we consider how we will address issues in the event of severe weather, issues in the supply chain or in the case of a reduction in available operatives to deliver the service.
  1. Severe Weather and Salt Shortages 
    Contingency Winter Service planning for severe and prolonged weather conditions or salt shortages include salting a Minimum Winter Network whereby priority will be given to a Minimum Winter Network route. This Minimum Winter Network is a subset of the primary treatment network and will provide a minimum essential service to the public, including links to the strategic network, access to key facilities and other transport needs.

    In such circumstances, it should be noted that all the available resources will be concentrating on keeping the minimum winter network cleared and therefore no timescales will be given for the clearance of lower priority routes.

    Given the scale of financial and other resources involved in delivering the Winter Service it is not reasonable either to; provide the service on all parts of the network; ensure running surfaces are kept free of ice or snow at all times, even on the treated parts of the network. The treatment of these will be as per the Minimum Winter Network salting routes and treatment times will be extended. Close liaison will be maintained with the Police and during such conditions. Additional resources will be deployed on a needs basis using other Council departments and external contractors as appropriate.

    Consideration will also be given to the conservation of salt stocks during such circumstances, either due to prolonged periods of severe weather conditions or where there is a risk to salt supplies. The Duty Officer and Winter Service Management team will aim to maintain salt stock between the levels of 3,000 tonnes and 4,500 tonnes until the end of January where it will be allowed to reduce to a minimum level of 1,500 tonnes at the end of the winter period. This will be monitored and managed day to day to maintain this level for the duration of these months. Should salt stocks deplete below the level of 3,000 tonnes, and where appropriate sand/salt mixes and salt alternatives need to be used, this will be determined on a risk assessment approach by the Duty Officer in relation to salt stocks, within the defined thresholds detailed in Table (F) below. As the salt stock falls below the specified levels, the level of treatment will reduce to maintain a minimum winter network for the delivery of the winter service.

    Table (F) Stock Resilience
     
    Salt stock
    levels
    Primary
    carriageway
    routes
    Secondary
    carriageway
    routes
    Minimum
    Winter
    Network
    Routes
    Footway
    Primary
    Footway
    Secondary
    Grit Bins
    4500T + Salt Salt N/A Salt Salt Salt/sand
    3000T
    -4500T
    Salt Salt N/A Salt  Salt Salt/sand
    1500T –
    3000T
    Salt Salt/sand N/A Salt Salt/sand Salt/and
    1000T –
    1500T
    Treat
    minimum
    network only
    Treat
    minimum
    network only
    Salt Salt.sand Sand Salt.sand
    500T –
    1000T
    Treat
    minimum
    network only
    Treat
    minimum
    network only
    Salt/sand Sand Sand Sand only until
    stock levels
    allow
    0T – 500T Treat
    minimum
    network only
    Treat
    minimum
    network only
    Salt/Sand or
    sand only at
    zero tonnes
    Sand Sand Sand only until
    stock levels
    allow


    The Winter Maintenance Management team will collate and coordinate a stand-by rota covering Duty Officers, Team Coordinators and Operatives for the Winter Service period. The stand-by period will commence early October and continue through to the end of April, however, this period may be altered should conditions dictate.

    The operational response will be supported through the wider Roads and Environment Services Structure as and when required with a view to ensuring:

  • Employees availability throughout defined risk periods
  • The necessity for the treatment operations to be co-ordinated and supervised
  • Resources and equipment availability for treating carriageways, footways and cycle routes
  • Appropriate resources available for dealing with vehicle breakdowns, problems with fuel supply and communications failure
  • Resource availability for the storage, delivery and loading of salt

These will be made in consideration with the following:-

  • Implications of Drivers’ Hours Regulations
  • Extent and nature of double manning and driver support
  • Shift system arrangements
  • Provision for holidays and sickness

In respect of the above considerations, the following will apply:

  • All carriageway salting routes will be single manned
  • During snow clearing operations, however, all salting routes will be double manned
  • All footway salting routes will be double manned i.e., tractor and pick-up drivers
  • Should additional footway crews be required for hand casting operations then
  1. Pandemic Resilience 
    The Service has reviewed the current internal Operational Winter Maintenance procedures and has identified a number of potential risks should large numbers of staff require to self-isolate or become ill due to a Pandemic Event.

    The risks identified include:
  • ​​​​Drivers – illness among trained LGV drivers may affect the Service’s ability to undertake our statutory obligations.
  • Depot – multiple infections and contamination could potentially lead to a depot shut down, again affecting the Service’s ability to undertake our statutory obligations.
  • Vehicles – the fleet is maintained and serviced throughout the winter period, so the same issue applies to our Fleet Maintenance Team based at Hilton Depot. Any loss of staff could lead to a potential depot closure and may affect the Service’s ability to undertake our statutory obligations.
  • Salt – our salt supplies come from Northern Ireland and if there was any pandemic impact at source or through the supply chain this may affect the Service’s ability to undertake our statutory obligations.
  • PPE – our PPE supplies come via various sources and if there was any pandemic impact at source or through the supply chain this may affect the Service’s ability to undertake our statutory obligations.

It is essential that the Service establishes. suitable safety control measures within our operations to respond to the potential restrictions placed upon the service because of a pandemic.

The service has amended its operational procedures to minimise close contact of employees and reduce the likelihood of internal cross contamination amongst drivers and other associated staff.

These measures include actions such as

  • Single person vehicle occupancy will be observed as much as possible, particularly in treatment of primary routes.
  • Additional cleaning of vehicles - it will be the driver’s responsibility to clean all touch points at the start and end of each shift.
  • Staggered start times and finish times – drivers will start work in small groups with 10-minute intervals to minimise potential close contact with their co-workers.
  • Use of alternative start location where possible – identify alternative start locations with appropriate facilities to minimise contact within a single depot location.

These measures are designed to reduce the likelihood of drivers becoming infected but also to reduce the impact on the delivery of the Winter Service from the need for drivers to self-isolate via a potential work contact.

Whilst the above will mitigate the impact of any isolated cases, we must also take into consideration the possibility of larger outbreaks of the virus within the community and the effect that may have on the resources available to deliver the service. Council employees may be affected via family contacts or have to self-isolate because of external causes.

  1. Assistance by Others 
    Where resources difficulties are identified efforts will be first made to seek assistance from across the wider Roads and Environment Service as well as across the other Council Services as a whole. Where skill levels and departmental service requirements are unable to assist, the Roads Network Team will engage with external suppliers to locate the additional operatives required to assist with the winter treatment.
     
  2.  Hierarchy of Treatments 
    If, after all other areas of support are exhausted and resource levels drop below those required to continue delivering the full Winter Service the available resources will be directed to those areas of highest priority, based on the risk posed to the road user.

    Ultimately whilst the treatments to both the carriageway and footway will depend very much on the skill set available with the resources i.e. carriageway will require HGV drivers, treatments will be prioritised in accordance with the Hierarchy of Treatments shown below.

    TABLE (G) – HIERARCHY OF TREATMENT

    Table G - Resiliance levesl showing priority and actions

    TABLE (H) – HIERARCHY OF TREATMENT

    Gritting treatment routes of roads and filling of grit bin resources

    It is has been held reasonable by the courts that footways are of a lower priority than carriageways on the basis that a skidding vehicle poses a greater risk than that of pedestrians. This is because they can identify and respond to snow and ice issues and can take precautionary measures to address these more easily than a vehicle. It is important, therefore, that priority is given to our Winter Resilience Routes and Primary Gritting Routes.

    The Secondary Carriageway Routes (as described in Table C) are primarily smaller residential roads with no public transport routes and lower gradients than those included in the Primary Routes and pose a smaller risk as vehicles generally only have to travel short distances on untreated roads to reach a treated part of the network.

    The Primary Footway Routes provide (as described in Table E) includes routes to schools, main shopping areas, town centres and main facilities and pose a higher risk than the treatment of our Secondary Routes due to the higher volume of use.
     
  3. Road Closures
    In periods of especially severe weather, temporary road closures may be necessary. In determining the optimum location consideration should be given to the availability of alternative routes and, if necessary, holding areas.

    When snow conditions have rendered a route unsafe for use where possible it will be closed to all traffic. The closure of a road in these circumstances must only be carried out on the instruction of the Police. Accordingly, close liaison must be maintained with them to confirm any decision to close a route. Routes closed by Police instruction must only be re-opened on Police instruction.

    The Roads and Environment Lead must be informed as soon as possible of any roads closed by the prevailing weather conditions and must also be consulted on any diversion route necessitated as a result of such a closure. In such instances, the Severe Weather Communication and Escalation protocol would be evoked to provide updates to all key stakeholders. As part of this protocol, details of the closure will be made available to the public via the Council’s website and social media.

    The prioritisation of the snow clearing from closed roads will be determined using the hierarchy of inspection and in partnership with the Health and Social Care partnership and the Emergency services to ensure vulnerable users can be accessed. Particular focus will also be given to ensure that rural communities are not cut off.

    It will be the responsibility of the Police to liaise with adjacent Police authorities on any closures and, with the assistance of the Communications team, updates will be periodically issued with regards to road closures.
  1. Arrangements for Ploughing and Continuous Gritting
  • Rostered stand-by personnel will respond to emergency call-outs and proceed to deal with any winter maintenance emergency, as instructed. Where prolonged overnight operations require stand-by personnel to be relieved then any subsequent treatment will require relief operatives to provide assistance. The ability of the Roads and Environment Service to deliver Winter Service is inevitably limited by the availability of suitably trained and experienced employees.
  • During continuous operations, in particularly adverse conditions, the working hours of the Duty Personnel should be closely monitored.
  • A general exemption from Driving Regulations is permitted to deal with winter service emergencies. All time, in excess of the normal daily driving limits, must however be spent dealing with emergency situations.

On occasion second men may be required when undertaking plough operations.

  1. Public Holidays
    During the Christmas and New Year Public Holidays, when priority route treatment will be carried out on a call-out only basis, unless weather conditions warrant there will be no pre-arranged stand-to or patrols. The Roads and Land Manager will circulate details, in early December, of the rostering arrangements for the Christmas and New Year period.
     
  2. Additional Resources 
    Should any weather event reach such a level as to prevent other Council departments carrying out their normal day-to-day duties, these additional resources will be directed to assist with the Council’s gritting operations of key strategic locations.
     
  3. Plant
    Fleet Services will carry out pre-winter checks on all vehicles and plant required for Winter Service treatment as per section 3.4. If necessary, further mid-season checks and equipment calibration will be arranged. All vehicles and plant are to be routinely maintained throughout the Winter Service period. Priority is to be given to repairs to Winter Service equipment during the winter period by our Council’s Fleet Service.

    A list of the plant available for the Winter Service is given in Appendix B of this document.
     
  4. Warning Signs 
    Throughout East Dunbartonshire, there may be locations where drainage problems exist resulting in wet areas on the public roads. Unfortunately, it is not possible to permanently resolve all of these prior to the onset of the overall winter period(s) and thus until such time as drainage repairs can be undertaken, arrangements will be made to locate ice warning and flooding signs at wet spots of which the Council is aware of and which are deemed to pose a significant risk
     
  5. Salt 
    Rock salt is the prime material for dealing with ice and snow on roads but can have environmental consequences. Rock Salt by its nature is hydroscopic and requires moisture to allow it to work effectively. It can adversely affect vegetation, pollute watercourses and leave a residue on footways. It can also damage the road structure, bridges and structures, utility apparatus and vehicles. However, used responsibly it can have minimal environmental impact. In the interests of sustainability, therefore only the minimum of salt will be used to deal with the prevailing conditions.

    The variable nature of the conditions during the Winter Service period makes it very difficult to specify the exact rate of salt spread. Notwithstanding, the rates of spread detailed in the Table (A) should be used wherever possible.
  1. Severe Wet Weather and Flooding 

    The Council has a responsibility in the event of heavy rainfall or flooding and in the event of any flood alerts being issued by SEPA it is important that measures are put in place to minimise the impact to the road network.

    On such occasions the Winter Maintenance Team will arrange for the existing road gullies to be cleaned at any known trouble areas prior to expected conditions and when possible, for any leaf fall to be cleaned.

    If the weather forecast is expected to be particularly severe then floodgates located at the locations below may be erected and road closures put in place to protect road users. The Severe Weather protocol will be activated at these times to ensure road users are aware of the dangers and any restrictions in place.

    Whilst the sole responsibility for protection of private property in the event of a flood lies with individual owners and not the Council or any other Agency, the Council will support the local community in preparing for and dealing with floodwaters with the supply of sandbags. The Council will also support and encourage local communities and businesses to prepare their own flood risk action plan to deal with emergencies likely to affect them.

    The deployment of sandbags will be based on the following priorities:
  1. To prevent loss of life or serious injury
  2. Maintaining access for emergency services
  3. Protecting vital facilities within the community, i.e. emergency service facilities; publicly owned old peoples’ establishments; etc.
  4. Protection of East Dunbartonshire Council’s community properties, such as schools and other public buildings, if appropriate
  5. Protection of Residential Property within the area
  6. Protection of Business/Commercial property within the area

If a flood event is anticipated sandbags will be delivered to those locations deemed ‘At Risk’ of being affected by floodwater and East Dunbartonshire Council will maintain a register of these locations. During flooding events the roads service can be stretched to try and help at various locations throughout the council area, therefore the Council will encourage residents to pick up sandbags for their own use at the Broomhill depot. Even if the location is deemed “at risk” no guarantee can be given that sandbags will be delivered within a specific timescale.

Requests for provision of sandbags can be made to the Council by calling 0300 123 4510. The Emergency Duty Officer or the Emergency Planning Officer will authorise distribution of sandbags in accordance with the priorities above.

The property owner/occupier is responsible for placing sandbags and providing other preventative measures. Sandbags are regarded as a short-term, temporary solution to the problem of flooding. The use of Floodwater Protection Schemes for low-level flood events of limited extent is recommended. For extensive areas of inundation, of significant scale, the Council may seek to promote a Flood Prevention (Mitigation) Scheme.

The use of sandbags is not favoured as a long-term solution for the following reasons:

  • Filled sandbags are heavy and awkward to lift. Care is required when placing them as injury could result
  • Sandbags have a limited life, as they degrade in sunlight
  • In use sandbags may become contaminated and be a hazard to health. Contaminated sandbags must be disposed of in a responsible manner by the householder not the council
  • It is recommended that sandbags are not re-used

East Dunbartonshire Council’s Roads Service will maintain a stock of sandbags to meet emergency needs and will work closely with other agencies during a flood event.

Stockholding of Sandbags

  • The Council will retain 500 filled sandbags at its Broomhill Depot in Kirkintilloch
  • The Council will maintain a stockholding of 3000 unfilled sandbags, with sufficient sand for filling them
  • Should circumstances require these additional sandbags to be filled resources will be allocated based on the operational priorities at that time

The distribution of sandbags will be the sole responsibility of the Roads Duty Manager, who will allocate sandbags in accordance with the priorities of this policy and knowledge of other operational requirements.
 

  1. Operational Reporting & Retention of Records 

    Throughout the Winter Service period, the authority will continually monitor performance during service delivery and respond effectively to changing conditions or network incidents. Comprehensive and accurate records should be kept of all Winter Service activity, including timing and nature of all decisions, the information on which they were based, and the nature and timing of all treatment, including routes salted, quantities of salt used, times of operations, resources utilised (plant and labour), any road closures, additional resources used and detail of any other significant problems encountered. 

    Roads Network Operations will be responsible for preparing and retaining the following records for a minimum period of five years:
  • Met desk forecasts including all updates
  • Decisions taken based on Met desk forecasts
  • Decisions taken based on other reports e.g., Police or Call Centre Reports
  • Maximum and minimum air temperatures recorded during any action
  • Details and timings of routes salted

Records from the Council’s ice detection stations are held by the service provider.

Any major incidents should be reported as soon as practically possible to the Roads and Transportation Lead. The Duty Officer will ensure, with the support of the wider team, the production and retention of these reports.
 

  1. Post Snow Clearance and Maintenance 

    Immediately following the completion of snow clearance operations, priority should be given to the clearance of gullies and off lets to ensure that melt water from snow on verges and islands or central reservations can quickly drain away.

    The clearance activity will be prioritised in accordance with primary routes and known trouble spots, such as at risk of flooding routes. However, it may be especially difficult to prevent melt water which is running across the carriageway from freezing and several applications of salt may be necessary.

    It will also be necessary to inspect the network to ensure that any damage is dealt with either as a defect or as programmed maintenance as appropriate and as resources permit. The inspection should be treated as a special safety inspection and deal with the items usually  included. Special attention should be given to the routes treated and the following items:
  • Removal of accumulations of grit from running surfaces and drainage channels
  • Inspection and clearance of all bridges, culverts and drainage systems liable to flooding
  • Inspection for frost effects and any damage caused by Winter Service equipment
  • Check and replenish salt stocks in depots and grit bins, and
  • Inspect, clean, lubricate, check and repair all vehicles and plant

In addition, it will be important to debrief all personnel involved to ensure that their experience and observations are recorded. These should be used to inform the Annual Service Review and contribute to the process of continuous improvement.
 

  1. Annual Review 

    All aspects of the Winter Service Policy, including service delivery arrangements, should be reviewed annually to take account of changing circumstances. All vehicles, plant, fuel provision, equipment and maintenance arrangements should be checked annually and in accordance with manufacturers’ requirements to ensure that any necessary action can be taken to ensure full operational service status prior to the Winter Service season. This should include checking the calibration of all de-icing equipment and spreaders. Authorities should review the administrative and management arrangements for Winter Service annually. This should include the use of all support services.

    The Annual Review will include an analysis on whether service delivery meets the Winter Service Policy standards and objectives. It will also take account of developments with regards to the impact of climate change. Service efficiency improvements such as route optimisation will also be considered.

Appendix A – Current Arrangements with Adjacent Councils 

Roads to be treated by Adjacent councils Roads to be treated by East Dunbartonshire Council
North Lanarkshire Council
No formal agreement with NLC
North Lanarkshire Council
East Dunbartonshire Council will grit the Kirkintilloch Link Road (Initiative Road) from its boundary with NLC to the Hornshill Roundabout
1. B802 Constarry Rd (small section is EDC)
2. B8048 Drumgrew Rbt (small section over railway bridge)
3. Twechar Rd 4. A80 W to Craiglinn Rd
5. C Chryston Rd 6. C Muckcroft Rd
7. C Burnbrae Rd 8. C Westerhill Rd
9. A806 Initiative Rd (EDC to boundary only)
10. B787 Auchinloch Rd (EDC to boundary only)
11. B812 Crosshill Rd (boundary is in middle of road and both treat)
12.B8023 Twechar Rd (EDC boundary only
13. A803 Glasgow Rd (EDC boundary only)

Glasgow City Council

  1. A879 Balmore Road – small section south of Allander Toll roundabout.
     
  2. Colston Road – from Kirkintilloch Road westwards to Railway Bridge at boundary.
     
  3. Boclair Road – GCC to grit from Allander Toll west towards Boclair Farm

Glasgow City Council

  1. Balmuildy Road – from boundary westwards to Balmore Road.
  2. Colston Road – from Balgrayhill Road westwards to Kirkintilloch Road.
  3. Boclair Road – EDC to grit from Boclair Farm east to Allander Toll
  4. Switchback Road – from boundary to Islay Avenue, Islay Avenue and part of Islay Road.
    1. Westerton Avenue – Westbound section along Switchback Road.
West Dunbartonshire Council
Cochno Road – Between boundary to Duntocher Road
West Dunbartonshire Council
Duntocher Road – between boundary and Faifley Road
Stirling Council
No reciprocal arrangements in place.

Stirling Council

  1. Crow Road B822 – EDC only grit to boundary.
  2. Strathblane Road A891 – EDC only grit to boundary.
  3. Stockiemuir Road A81 – EDC only grit to boundary.
  4. Mugdock Road – EDC only grit to boundary.


Appendix B – Plant and Transport 

Description Weight Capacity Number of vehicles
Large Gritters 26T 9m3 2
Medium Gritters 18T 6m3 4
Small Gritters 14T 3m3 8
Small Tippers 7.5T 2m3 5
Tipper vans 3.5T 1m3 6
Footway Tractors     10
JCB 3CX     1
Loading Shovel     1
JCB 3CX Compact     2


Appendix C – Spread Rate Chart 

This table gives an indication of the weight of salt that must be added to an empty gritter to treat each route. A full bucket of salt weighs approximately 1500 kg.

The combined weight of lorry, spreader, salt, plough (if fitted) and driver must not exceed the maximum GVW of the vehicle. (see Appendix D). In some cases, it might not be possible to complete all parts of  the route(s) without re-loading.
 

Route Treated length Salt Required (kg)
Route Treated Length
Km
10g/m² 15g/m² 20g/m² 30g/m²
R1 66.1 3.09 4.64 6.18 9.27
R2 71.5 3.21 4.82 6.42 9.63
R3 56 2.87 4.31 5.74 8.61
R4 52 2.67 4.01 5.34 8.01
R5 49.5 2.79 4.19 5.58 8.37
R6 55.7 2.59 3.89 5.18 7.77
R7 37 2.12 3.17 4.23 6.35
R8 40.2 2.27 3.99 4.53 6.80


Appendix D – Vehicle Weights and Capacities 

Those highlighted in Red will require use of a larger vehicle to complete route or return to the depot to refill.

Routes Vehicle weight Unladen weight Capacity Target Weights
Gritter
Route
Gross Vehicle weight Chassis + Gritter
unladen
Max Salt Capacity 10g/m² 15g/m² 20g/m² 30g/m²
1 26T 14.7 11.3 17.79 19.34 20.88 23.97
2 18T 8.9 9.1 12.11 13.72 15.32 18.53
3 18T 8.9 9.1 11.77 13.21 14.64 17.51
4 18T 8.9 9.1 11.57 12.91 14.24 16.91
5 14T 7.8 6.2 10.59 11.99 13.38 16.17
6 14T 7.8 6.2 10.39 11.69 12.98 15.57
7 14T 7.8 6.2 9.92 10.97 12.03 14.15
8 18T 8.9 9.1 12.89 12.89 13.43 15.70


Appendix E – Grit Bin Application Criteria 

Any requests for additional grit bins should meet the following criteria:

  1. The proposed location will be on a public road or footpath.
  2. Any location which has a steep gradient or topographical feature which merits consideration. Typically gradients greater than 1:17.
  3. The proposed location must service and be of benefit to several properties (applications will not normally be considered where only an individual property is being serviced)
  4. The proposed location must be accessible for cleaning and filling the grit bin.
  5. Siting of a grit bin must be agreed by at least six residents. This must include those residents directly affected i.e. access or frontage of the new bin location.
  6. There is no alternative provision of a grit bin within 300m of the requested location.
  7. Requested location does not form part of a primary gritting route.

An application form can be downloaded from the Council’s website.

East Dunbartonshire Council reserves the right to remove a grit bin at any time for whatever reason. The Council will maintain the grit bins, i.e. refill, clean the bins of refuse and repair or replace damaged bins as resources permit.

Grit bins will remain in position all year. Only in exceptional cases, where it is established that they are being subjected to vandalism, would consideration be given to removing them outwith the winter period.

In addition to the grit bins which are strategically placed throughout East Dunbartonshire, members of the public may also uplift small quantities of grit (up to 50kg) free of charge from Broomhill Depot, Broomhill Industrial Estate, Kilsyth Road, Kirkintilloch, G66 1TF and Langfaulds Cemetery, Baljaffray Road, Bearsden, G61 4PU.

The public will be responsible for supplying a suitable container. Local businesses will not be permitted to uplift grit from these locations.