STORM BOELO - The Met Office’s Yellow Weather warning for strong winds has been upgraded to Amber from 9pm on Saturday (24 October) and is due to last until 9pm on Sunday 25 October. Over the coming days and hours Council teams will be responding to any incidents that may occur as a result of the storm including flooding and fallen trees.

You can report flooding or fallen trees to us online.

However, you can let us know about emergency incidents such as a fallen tree blocking a road by calling 0300 123 4510. 

  • Report by:

    Ann Davie, Chief Executive

  • TN Number:

    080-26

  • Subject:

    Westerton Primary School

  • Responsible Officer:

    Alan Bauer, Executive Officer - Assets & Facilities

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.

  • The purpose of this Technical Note is to update Elected Members on the anticipated project timetable for the Westerton Primary School Project
  • On 5 March 2026 the Council approved the 10-year Capital Investment Plan report EDC/001/26/AD, allocating £3m to complete all pre-construction activities for the proposed new Westerton Primary School.  Officers are in the process of finalising the procurement arrangements required to formally appoint a design team and managing contractor for the project
  • The indicative programme for the project is as follows:

Indicative programme

Indicative programme
Stage Dates

RIBA 2 Concept Design 

August – October 2026

RIBA 3 Design

November – February 2027

RIBA 4 Detailed Design

March 2027 – October 2027

Planning Application Submission

April 2027

Construction Tender Period

July 2027 – October 2027

Construction Start

January 2028

  • Initial stakeholder engagement will be undertaken with education stakeholders and the general public in September/October 2026, with further engagement thereafter undertaken in-line with key design development milestones and planning application milestones
  • Members should note the dates at Section 3 above remain indicative and subject to change with a particular dependency on the timing of the appointment of the design team and managing contractor.  Construction start date is dependent upon Council approval to proceed to contract close
  • Regular updates on the project, including any changes to the anticipated project programme, will be communicated via the General Fund Capital monitoring report submitted to the Policy & Resources Committee