Due to operational issues, regrettably, some of our food waste collections have been suspended. If your food caddy is not collected on its scheduled day, please take your bin in and present it on your next collection day. We apologise for the inconvenience this will cause and we’re working hard to remedy the situation.

  • Report by:

    Ann Davie, Chief Executive

  • TN Number:

    080-26

  • Subject:

    Westerton Primary School

  • Responsible Officer:

    Alan Bauer, Executive Officer - Assets & Facilities

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.

  • The purpose of this Technical Note is to update Elected Members on the anticipated project timetable for the Westerton Primary School Project
  • On 5 March 2026 the Council approved the 10-year Capital Investment Plan report EDC/001/26/AD, allocating £3m to complete all pre-construction activities for the proposed new Westerton Primary School.  Officers are in the process of finalising the procurement arrangements required to formally appoint a design team and managing contractor for the project
  • The indicative programme for the project is as follows:

Indicative programme

Indicative programme
Stage Dates

RIBA 2 Concept Design 

August – October 2026

RIBA 3 Design

November – February 2027

RIBA 4 Detailed Design

March 2027 – October 2027

Planning Application Submission

April 2027

Construction Tender Period

July 2027 – October 2027

Construction Start

January 2028

  • Initial stakeholder engagement will be undertaken with education stakeholders and the general public in September/October 2026, with further engagement thereafter undertaken in-line with key design development milestones and planning application milestones
  • Members should note the dates at Section 3 above remain indicative and subject to change with a particular dependency on the timing of the appointment of the design team and managing contractor.  Construction start date is dependent upon Council approval to proceed to contract close
  • Regular updates on the project, including any changes to the anticipated project programme, will be communicated via the General Fund Capital monitoring report submitted to the Policy & Resources Committee