Technical Notes 2026, Issue 80 - Westerton Primary School
- The purpose of this Technical Note is to update Elected Members on the anticipated project timetable for the Westerton Primary School Project
- On 5 March 2026 the Council approved the 10-year Capital Investment Plan report EDC/001/26/AD, allocating £3m to complete all pre-construction activities for the proposed new Westerton Primary School. Officers are in the process of finalising the procurement arrangements required to formally appoint a design team and managing contractor for the project
- The indicative programme for the project is as follows:
Indicative programme
| Stage | Dates |
|---|---|
|
RIBA 2 Concept Design |
August – October 2026 |
|
RIBA 3 Design |
November – February 2027 |
|
RIBA 4 Detailed Design |
March 2027 – October 2027 |
|
Planning Application Submission |
April 2027 |
|
Construction Tender Period |
July 2027 – October 2027 |
|
Construction Start |
January 2028 |
- Initial stakeholder engagement will be undertaken with education stakeholders and the general public in September/October 2026, with further engagement thereafter undertaken in-line with key design development milestones and planning application milestones
- Members should note the dates at Section 3 above remain indicative and subject to change with a particular dependency on the timing of the appointment of the design team and managing contractor. Construction start date is dependent upon Council approval to proceed to contract close
- Regular updates on the project, including any changes to the anticipated project programme, will be communicated via the General Fund Capital monitoring report submitted to the Policy & Resources Committee