• Report by:

    Ann Davie, Chief Executive

  • TN Number:

    070-26

  • Subject:

    Roads & Neighbourhood Services 2026/27 Carriageway and Footway Resurfacing Programme

  • Responsible Officer:

    Thomas McMenamin, Executive Officer – Roads & Neighbourhood Services

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.

  • The purpose of the Technical Note is to provide Members with an overview of the 2026/27 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme
  • The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication of when this work is programmed to be undertaken Although this may change throughout the year
  • In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site
  • All works will or have already been logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency work by the Service and/or utility providers may be prioritised
  • The Service will provide a further quarterly progress update via Technical Notes in July 2026, October 2026, and January 2027 along with a final update in April 2027
  • The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies
  • Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created
  • The undernoted table shows the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.

Carriageway Resurfacing - Milngavie

Milngavie

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Milngavie
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Strathblane Road (Phase 2)

Internal resources

1

-

100m north of Marchfield to Scottish Water access 

Craigmaddie Road

Internal resources

-

A81 to 400m before Tower Road 

Hilton Road

 

Internal resources

3

-

-

Kirk St

 

Internal resources

4

-

-

Finlay Rise (phase 1) including Auchencruive

Internal resources

4

-

-

Finlay Rise (phase 2, including Bridgegait)

Internal resources      

4

-

-

Carriageway Resurfacing - Bearsden North

Bearsden North

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bearsden North
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Stockiemuir Road (phase 5)

Internal resources

1

20 April 2026

From Craighead drive toward Craigton - 300m length - include RB

Milngavie Road (phase 4)

Internal resources

1

-

Manse Road to Mosshead

Milngavie Road (phase 5)

Internal resources

1

-

Manse Road to Mosshead

Ballaig Avenue

 

Internal resources

3

-

-

Carriageway Resurfacing - Bearsden South

Bearsden South

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bearsden South
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Ballater Drive

Internal resources 

1

13 April 2026

Between Braemar and Coronation Way

Garry Ave

Internal resources

-

Substitute with Kilsyth Road

Carriageway Resurfacing - Bishopbriggs North & Campsie

Bishopbriggs North & Campsie

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bishopbriggs North & Campsie
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Kirkintilloch Road (phase 3)

Internal resources

1

-

Between Cadder R'bout & Westerhill Rd

Redmoss Road

 

Internal resources

1

-

TBC

Campsie Road

Internal resources

24 April 2026

Junction goes to golf club - 200m toward Torrance

Tower Road/Back O' Hill Road

 

Internal resources

3

-

-

Millburn Street

Internal resources

4

-

-

Carriageway Resurfacing - Bishopbriggs South

Bishopbriggs South

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bishopbriggs South
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Park Road

Internal resources

2

-

Hillside Dr to no. 143 (outside School)

Carriageway Resurfacing - Lenzie & Kirkintilloch South

Lenzie & Kirkintilloch South

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Lenzie & Kirkintilloch South
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Lenzie Road

Internal resources

1

-

Laurel Ave to Myrtle Ave

Woodilee Road

 

Internal resources

1

-

-

Lindsaybeg Road (phase 1) 

Internal resources

2

-

Auchinloch to Easter Garingaber Rd

Lindsaybeg Road (phase 2)

Internal resources

-

Easter Garingaber to roundabout

Watermill Ave (phase 1)

 

Internal resources

2

-

-

Watermill Ave (phase 2)+Farm Park+Millas Plc

 

Internal resources

2

-

-

Orchard Field

 

Internal resources

3

-

-

Glenwood Road

 

Internal resources

3

-

-

St Columba Drive

 

Internal resources

4

-

-

Moncrieff Avenue

 

Internal resources

4

-

-

Loch Road

 

Internal resources

4

-

Woodlee to Kirksyde Avenue

Willow Avenue + Cedar

 

Internal resources

4

-

-

Carriageway Resurfacing - Kirkintilloch East & North Twechar

Kirkintilloch East & North Twechar

the 2026/27 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Kirkintilloch East & North Twechar
Road Carriageway Resurfacing 2026/27 Quarter Date completed Comment

Kilsyth Road (phase 3 and 4)

Internal resources

1

-

Postponed to next year due to conflict with SGN work

Milton Road

Internal resources

1

-

From Glasgow RD to Bridge

Marmion Drive

Internal resources

1

-

Ongoing

Chryston Road

Internal resources

2

-

Rail bridge to Ruther Ave

Bellfield Road

 

Internal resources

2

-

-

Washinton Road

 

Internal resources

2

-

-

Waterside Road (phase 1)

 

Internal resources

2

-

Market to Merkland

Waterside Road (phase 2) 

Internal resources

2

 -

Outside Gartconner Primary School

Initiative road

Internal resources

2

-

All the legs to and from Lindsaybeg Roundabout

New Lairdsland Road

Internal resources

-

From Canal to Catherine St

Burnbrae Road (phase 2)

Internal resources

3

-

Bridge deck to Muckcroft Rd

Benvue Road - Lennoxtown

 

Internal resources

3

-

-

Waverley Crescent

Internal resources

3

-

-

Burnside Avenue

 

Internal resources

3

-

-

John Street

 

Internal resources

4

-

-

Badenoch Road, Loran Place, Badenoch Road

 

Internal resources

4

-

-

  • The under noted table shows the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.

Footway Resurfacing - Bearsden North

Bearsden North

the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bearsden North
Road Footway Resurfacing 2026/27 Quarter Date completed Comment

Roman Road

Internal resources

2

-

From School to Grange Road/Rail Bridge

Thorn Road

Internal resources

4

-

Thorn Drive to Golf club

Footway Resurfacing - Bearsden South

Bearsden South

the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bearsden South
Road Footway Resurfacing 2026/27 Quarter Date completed Comment

Milngavie road

Internal resources

1

Ongoing

MacFarlane mini roundabout to Kessington Hall+ Opp Asda

Inveroran Drive (phase 2)

Internal resources

1

-

Glendaruel Ave to Durness Ave-Both sides

Footway Resurfacing - Bishopbriggs South

Bishopbriggs South

the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bishopbriggs South
Road Footway Resurfacing 2026/27 Quarter Date completed Comment

Kirkintilloch Road

Internal resources

1

-

Meadow Burn to opp Westerhill Road-one side

Footway Resurfacing - Bishopbriggs North & Campsie

Bishopbriggs North & Campsie

the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Bishopbriggs North & Campsie
Road Footway Resurfacing 2026/27 Quarter Date completed Comment

Park Crescent

Internal resources

3

-

-

Main St - Torrance 

 

Internal resources

4

-

Kelvin Bridge RB to Campsie Rd

Footway Resurfacing - Milngavie

Milngavie

the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Milngavie
Road Footway Resurfacing 2026/27 Quarter Date completed Comment

South Main Road

Internal resources

2 and 3 

-

Full Length - both side- On hold due to finding coal tar- reviewing for surface treatment option by external contractor 

Footway Resurfacing - Lenzie & Kirkintilloch South

Lenzie & Kirkintilloch South

the 2026/27 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works - Lenzie & Kirkintilloch South
Road Footway Resurfacing 2026/27 Quarter Date completed Comment

Gallowhill Road (Phase 1)

 

Internal resources

2

-

Beech to Moss

Elm Ave

 

Internal resources

2

-

Beech Road to Number 6

Gallowhill Road (Phase 2)

Internal resources

3

-

Kirkintilloch Road to Beech-Both sides

  • At this stage, there are no carriageway resurfacing works planned for 2026–2027 at known coal tar-impacted locations. Should any work be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes
  • At this stage, there are no Footway resurfacing works planned for 2026–2027 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes
  • In summary, the Service is commencing the year with the aspiration to complete the 46 carriageway and 11 footway locations listed but will add others if additional external resources can be secured during the financial year.