• Report by:

    Ann Davie, Chief Executive

  • TN Number:

    022-26

  • Subject:

    Roads & Neighbourhood Services 2025/26 Carriageway and Footway Resurfacing Programme (Quarter 3 Update)

  • Responsible Officer:

    Thomas McMenamin, Executive Officer – Roads & Neighbourhood Services

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared outwith the Council.

The purpose of the Technical Note is to provide Members with an overview of the 2025/26 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme.

The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication of when this work is programmed to be undertaken.

In addition, the tables also highlight which locations have tested positive for the presence of coal-tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.

All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency work may be prioritised.

The Service will provide a final quarter 4 update in April 2026.

The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.

Cold Tar Testing is a requirement for planned resurfacing work that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.

The under noted table shows the 2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.

Milngavie

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Stockiemuir Road (phase 4)

Internal Resources 

1

09/06/2025

Strathblane Road (Phase 1) 

 Internal Resources

1

23/06/2025

 From no.1 to no.37

Campsie Drive

Internal Resources

3

17/11/2025

Cloberfield / Clober road phase 2

Internal Resources

4

Crossveggate

Internal Resources

4

Main Street

Internal Resources

4

Mosshead to Burnbrae roundabout

Bearsden North

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Baljaffray Road (phase 4) Duntocher roundabout

Internal Resources 

1

19/05/2025

Duntocher Road (phase 1)   

 Internal Resources

1

30/05/2025

Duntocher Road (phase 2)   

 Internal Resources

1

30/05/2025

Golf View park crescent

Internal Resources

2

15/09/2025

Boclair Road (phase 3)

Internal Resources

2

16/10/2025

Boclair Road (phase 4)

Internal Resources

2

16/10/2025

Moorfootway

Internal Resources

3

24/11/2025

Fintry Garden + Paterson Place

Internal Resources

3

24/11/2025

Culloch Road

Internal Resources

3

12/12/2025

Thorn Drive

Internal Resources 

4

Ralston Road

Internal Resources 

4

Gartconnell Road

Internal Resources 

4

Carse View

Internal Resources 

4

Bearsden South

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Milngavie Road (phase 3)

Internal Resources 

1

16/04/2025

McFarlane mini roundabout to Kessington

Maryhill Road

 Internal Resources

3

24/10/2025

Maxwell Avenue

Internal Resources

3

10/11/2025

GCC boundary to Care home

Bishopbriggs North and Campsie

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Kirkintilloch Road

Internal Resources 

1

29/04/2025

Milton Road - Lennoxtown

 Internal Resources

1

13/06/2025

Meadowburn

Internal Resources

2

25/08/2025

Balmuildy Road

Internal Resources

2

22/09/2025

Dalkeith Avenue

Internal Resources

3

31/10/2025

South Crosshill Road – from A803 to mini-roundabout

External Resources 

4

Contractor to confirm start date

Park Road – from A803 to Hillside Drive junction 

External Resources 

4

Contractor to confirm start date

Bishopbriggs South

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Crowhill Road

Internal Resources 

1

04/04/2025

Partially completed as found issue with Scottish Water apparatus. It is our intention to complete the resurfacing of this section of Crowhill Road once we have confirmed that all Scottish Water sewer repairs are finished.

Angus Avenue

 Internal Resources

1

11/07/2025

Kenmure Lane

Internal Resources

3

09/01/2026

Lenzie And Kirkintilloch South

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Lenzie Road

Internal Resources 

2

08/09/2025

Regent Square + Glenbank Rd

 Internal Resources

2

28/08/2025

Burnbrae Road

Internal Resources

3

25/09/2025

Carron Crescent + Birken Road

Internal Resources

3

20/10/2025

Parkburn Avenue

Internal Resources

3

01/12/2025

Southbank Drive

Internal Resources

4

Millersneuk Road – from Auchinloch Road to Millersneuk Drive junction

External Resources 

4

Contractor to confirm start date

Bishopbriggs North and Campsie

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Kilsyth Road

Internal Resources 

1

09/05/2025

Redbrae Road

 Internal Resources

1

27/06/2025

Newdyke Road

Internal Resources

2

18/07/2025

Main Street - Twechar

Internal Resources

2

05/09/2025

The under noted table shows the 2025/26 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.

Bearsden North

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Rosslynn Road

Internal Resources 

1

04/08/2025

From Castlehill School to Dryburgh Road on both sides.  The footway resurfacing, originally scheduled for next year was brought forward to this year and will replace the previously planned works on Gallowhill Road. This change was made due to a conflict with utility works affecting Gallowhill Road, which has now been postponed to next year- Only one side resurfaced due to resources issue

Milngavie Road (phase 2)

Internal Resources 

2

30/09/2025

Mosshead to Manse-House side only

Bearsden South

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Inveroran Drive

 Internal Resources

1

15/05/2025

Milngavie Road

Internal Resources 

1

16/04/2025

MacFarlane mini-roundabout to Kessington shop- one side only

Drymen Road

Internal Resources

2

10/11/2025

Station Road to Cross

Bishopbriggs South

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Auchinairn Road

Internal Resources 

4

Kirkintilloch East & North & Twechar

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Fellview Avenue

Internal Resources 

3

03/11/2025

Alexander Place

 Internal Resources

3

16/12/2025

Park Street

Internal Resources

3

16/12/2025

Lenzie And Kirkintilloch South

2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2025/26 Quarter Date Completed Comments

Gallowhill Road

Internal Resources 

1

Postponed to next year 

The footway resurfacing originally scheduled for this year has been postponed to next year and replaced with Rosslynn. This change was made due to a conflict with utility work affecting Gallowhill Road.

Boghead Road

 Internal Resources

2

Abandoned

Postponed due to conflict with utility company

Craigenbay Road

Internal Resources

4

At this stage, there are no carriageway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.

At this stage, there are no Footway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any work be scheduled at these locations in future planning cycles, details will be 

In summary, the Service is commencing the year with the aspiration to complete the 49 carriageway and 11 footway locations listed but will add others if additional external resources can be secured during the financial year.