Technical Notes 2025, Issue 4 - Roads & Neighbourhood Services 2024/25 Carriageway and Footway Resurfacing Programme – Quarter 3 Progress Update
- The purpose of the Technical Note is to provide Elected Members with an update on the 2024/25 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme, following the completion of the second quarter of the financial year.
 - The Technical Note highlights the work programmes associated with internal and external resources, as well as providing an indication to when this work is programmed to be
 - In addition, the information also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from
 - All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
 - The Service will provide a final quarterly progress update via Technical Notes in March 2025.
 - The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
 - It should be noted that the programme and sequence of some locations have been altered from the previously issued Technical Note. This has been due to other works on the network impacting either directly on the planned location or the nominated diversion route. The team have attempted to substitute the locations and re-sequence the programme to ensure that the locations are caught later in the year.
 - Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
 - The undernoted information shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.
 
Milngavie
- Dumgoyne Avenue (Phase 2)
 
Internal resources
Q1
April 2024
- Ellangowan Road
 
Internal resources
Q2
August 2024
- Mugdock Road /Ellangowan Road – RB included
 
Internal resources
Q2
August 2024
- Keystone Quadrant
 
Internal resources
Q2
August 2024
- Drumlin Drive
 
Internal resources
Q2
Postponed - Positive Coal Tar Test
- Campsie Drive
 
Internal resources
Q3
October 2024
- McGrigor Road
 
Internal resources
Q3
November 2024
- Tambowie Crescent
 
Internal resources
Q3
December 2024
- Allander Road
 
Internal resources
Q4
Bearsden North
- Baljaffray Road (phase 3)
 
Internal resources
Q1
April 2024
- Stockiemuir Road
 
Internal resources
Q1
April 2024
- Russell Drive (phase 1)
 
Internal resources
Q1
June 2024
- Russell Drive (phase 2)
 
Internal resources
Q1
June 2024
- Milngavie Road (Phase 3) – BP Garage to Manse Road
 
Internal resources
Q3
October 2024
- Bailie Drive
 
Internal resources
Q3
October 2024
- Campsie Drive
 
Internal resources
Q4
Bearsden South
- Kessington Road (phase 2)
 
Internal resources
Q1
May 2024
- Afton Crescent
 
Internal resources
Q1
May 2024
- Boclair Road (phase 1)
 
Internal resources
Q1
June 2024
- Boclair Road (phase 2)
 
Internal resources
Q2
July 2024
- Ledi Drive
 
Internal resources
Q2
August 2024 - Brought forward from 2025-26 programme.
- Methven Avenue + Kenmore Gardens + Ardoch Road
 
Internal resources
Q3
November 2024
- Second Avenue
 
Internal resources
Q4
- Rannoch Drive (phase 2)
 
Internal resources
Q4
- Albert Drive
 
Internal resources
Q4
Bishopbriggs North & Campsie
- Juniper Drive
 
Internal resources
Q3
October 2024
- Forth Road/Queensview - Torrance
 
Internal resources
Q3
December 2024
- Craigmarloch Avenue -Torrance
 
Internal resources
Q3
Postponed due to resource issues - Some patching work done-will reschedule into 3 years program
- Old Balmore Road
 
Internal resources
Q4
- Campsie Road, Lennoxtown
 
Internal resources
Q4
Bishopbriggs South
- Springfield Square
 
Internal resources
Q1
May 2024
- Fintry Crescent and Tinto Road
 
Internal resources
Q1
June 2024
- Wester Cleddens Road
 
Internal resources
Q1
June 2024
- Crowhill Road (phase 1)
 
Internal resources
Q2
September 2024
- Crowhill Road (phase 2)
 
Internal resources
Q2
September 2024
- Angus Avenue
 
Internal resources
Q2
July 2024 Brought forward to July 2024 - Switch with Milngavie Road due to conflict with Canniesburn Toll
- Elspeth Gardens
 
Internal resources
Q3
December 2024
Lenzie & Kirkintilloch South
- Boghead Road (phase 2)
 
Internal resources
Q2
July 2024
- Kirkintilloch Road, Lenzie (phase 1)
 
Internal resources
Q2
September 2024
- Southbank Road
 
Internal resources
Q4
- Douglas Gardens; Place; Court; and Avenue
 
Internal resources
Q4
- Heather Gardens; Heather Place; and Forest Gardens
 
Internal resources
Q4
- Heather Drive, Heather Place
 
Internal resources
Q4
Kirkintilloch East & North Twechar
- Waterside Road (Phase 2-overlay)
 
Internal resources
Q1
April 2024
- Oxford Street
 
Internal resources
Q1
May 2024
- Kilsyth Road (phase 1)
 
Internal resources
Q1
June 2024
- Main Street (phase 1), Twechar
 
Internal resources
Q2
Postponed to 2025-26 - Replaced with Ledi Drive - due to conflict with new outdoor center in Twechar
- Main Street (phase 2), Twechar
 
Internal resources
Q2
Postponed to 2025-26 – Replaced with Ledi Dr- due to conflict with new outdoor center in Twechar
- Applecross Road
 
Internal resources
Q3
November 2024
- Braehead Street
 
Internal resources
Q3
November 2024
The undernoted information shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.
Milngavie
 
- Main Street (Kelvin Timber to Waitrose)
 
Internal resources
Q1
June 2024
- Mugdock Road
 
Internal resources
Q1
June 2024
- Station Road
 
Internal resources
Q2
August 2024
- Prestonfield
 
Internal resources
Q2
August 2024
Bearsden North
- Milngavie Road (Westside near Mosshead Road)
 
Between Kelvin Timber and Waitrose
Q1
Duplicate -This section is called Main St, and it has already resurfaced in May 2024
- Grampian Way
 
Internal resources
Q3
November 2024
Bearsden South
- Crarae Avenue
 
Internal resources
Q1
May 2024
- Westfield Drive
 
Internal resources
Q1
May 2024
- Maxwell Avenue
 
Internal resources
Q1
June 2024
- Drymen Road
 
Internal resources
Q2
Postponed Subject to Canniesburn Toll completion
- Killermont Road
 
Internal resources
TBC
TBC Possibly required to carry out with an external resource - cross over from 2023-24- Councilor’s list
Bishopbriggs North & Campsie
- Wester Cleddens Road
 
Internal resources
Q4
- Teviot Avenue
 
Internal resources
TBC Coal Tar found- External contractor instructed to carry work in 2024-25
- Allander Gardens
 
Internal resources
TBC Possible /required to carry out with an external resource- Cross over from 2023-24- Councilor’s list
Lenzie & Kirkintilloch South
- Kirkintilloch Road, Lenzie
 
Internal resources
Q2
July 2024
- Craigenbay Road
 
Internal resources
Q3
Postponed due to resource issues - Moved to 2025/26
- Laxton Drive
 
Internal resources
Q3
December 2024
- Bramley Place
 
Internal resources
Q3
December 2024
- Glenwood Road and Place
 
Internal resources
Q3
September 2024
The undernoted information shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.
Milngavie
 
- Clober Road
 
External resources
Q2
August 2024 - External contractor appointed to carry work in 2024-25
- Blackwood Road
 
External resources
Q2
August 2024 - External contractor appointed to carry work in 2024-25
- Dougalston Road
 
External resources
Q2
September 2024 - External contractor appointed to carry work in 2024-25
- Connell Crescent
 
External resources
Q2
September 2024 - External contractor appointed to carry work in 2024-25
Bishopbriggs South
- Brora Road & Crescent
 
External resources
Q2
September 2024 - External contractor appointed to carry work in 2024-25
- Coltpark Avenue
 
External resources
Q3
December 2024 - External contractor appointed to carry work in 2024-25
- Gannochy Drive
 
External resources
Q3
December 2024 - External contractor appointed to carry work in 2024-25
Bishopbriggs North & Campsie
- Teviot Avenue
 
External resources
Q4 - External contractor appointed to carry work in 2024-25
Lenzie & Kirkintilloch South
- Lithgow Avenue
 
External resource
Q4 - External contractor appointed to carry work in 2024-25
- Gallowhill Avenue
 
External resource
Q2
August 2024 - External contractor appointed to carry work in 2024-25
The undernoted information shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.
Bishopbriggs South
- Coltpark Ave
 
External resources
Q3
December 2024 - External contractor appointed to carry work in 2024-25
Bishopbriggs North & Campsie
- Meadowburn
 
External resources
Q3
October 2024 - External contractor appointed to carry work in 2024-25
The undernoted information shows the locations selected as part of capital carriageway resurfacing 2023 /24. Regrettably, these locations were not progressed as part of the 2023/24 programme due the identification of coal tar. The works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations require full tendering exercise and framework. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.
Bearsden South
- Durness Avenue (phase 1)
 
External resources
Completed March 2024 - Full length resurfaced
Bearsden North
- Lawers Drive
 
External resources
TBC
TBC
Bishopbriggs South
- Gannochy Drive
 
External resources
TBC
TBC - External contractor appointed to carry work in 2024-25
- Rannoch Gardens
 
External resources
TBC
TBC - External contractor appointed to carry work in 2024-25
- Lochy Gardens
 
External resources
TBC
TBC - External contractor appointed to carry work in 2024-25
- Maree Gardens
 
External resources
TBC
TBC - External contractor appointed to carry work in 2024-25
- Ness Gardens
 
External resources
TBC
TBC - External contractor appointed to carry work in 2024-25
The undernoted information shows the locations selected as part of capital footway resurfacing 2023-24. Regrettably, these locations were not progressed as part of the 2023/24 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations are required fully tendering exercise and framework. The information below shows the Council Ward, Carriageway Resurfacing 2024/25, Quarter, Date Completed, and Comment if required.
Milngavie
- South Mains Road
 
TBC
TBC
TBC - Investigation required for minor project based on desk top survey – subject to availability of budget
- Kelvin Road
 
External resources
TBC
TBC
- Crossburn Avenue
 
External resources
TBC
TBC
The Service has appointed an external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the pre-start meetings, the dates will be confirmed for sections 10, 11, 12, and 13.
In summary, the Service is commencing the year with the aspiration to complete the 63 carriageway and 25 footway locations listed but will add others if additional external resources can be secured during the financial year.