Technical Notes 2025, Issue 182 - Roads & Neighbourhood Services 2025/26 Carriageway and Footway Resurfacing Programme (Quarter 2 Update)
- The purpose of the Technical Note is to provide Members with an overview of the 2025/26 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme.
- The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication of when this work is programmed to be undertaken.
- In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
- All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The Service will provide a further quarterly progress update via Technical Notes in January 2026 along with a final update in April 2026.
- The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
- The under noted accordion shows the 2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Carriageway Resurfacing 2025/26 completed by internal resources
- Stockiemuir Road (phase 4), Quarter 1, Date complete 09/06/2025
-
Strathblane Road (Phase 1), Quarter 1, Date complete 23/06/2025, Comment: From no.1 to no.37
-
Campsie Drive, Quarter 3
-
Cloberfield / Clober road phase 2, Quarter 4
-
Crossveggate, Quarter 4
-
Main St, Quarter 4, Comment: Mosshead to Burnbrae roundabout
- Baljaffray Road (phase 4) Duntocher roundabout, Quarter 1, Date Completed 19/05/2025
- Duntocher Road (phase 1), Quarter 1, Date Completed 30/05/2025
- Duntocher Road (phase 2), Quarter 1, Date Completed 30/05/2025
- Golf View Park Cres, Quarter 2, Date Completed 15/09/2025
- Boclair Road (phase3), Quarter 2, Under Progress and expected to be completed by 24/10/25
- Boclair Road (phase4), Quarter 2, Under Progress and expected to be completed by 24/10/25
- Moorfootway, Quarter 3,
- Fintry Garden + Paterson Place, Quarter 3,
- Culloch Road, Quarter 3,
- Thorn Drive, Quarter 4,
- Ralston Road, Quarter 4,
- Gartconnell Road, Quarter 4,
- Carse View, Quarter 4,
- Milngavie Road (phase 3), Quarter 1, Date Completed 16/04/2025, Comment: McFarlane mini roundabout to Kessington
- Maryhill Road, Quarter 3, Comment: TBC
- Maxwell Ave, Quarter 3, Comment: GCC boundary to Care home
- Kirkintilloch Road, Quarter 1, Date Completed 29/04/2025
- Milton Road- Lennoxtown, Quarter 1, Date Completed 13/06/2025
- Meadowburn, Quarter 2, Date Completed 25/08/2025
- Balmuildy Road, Quarter 2, Date Completed 22/09/2025
- Dalkeith Avenue, Quarter 3,
- Crosshill Road, Quarter 4,
- Crowhill Road, Quarter 1, Date Completed 04/04/2025, Complete: Partially completed as found issue with Scottish Water apparatus- It is our intention to complete the resurfacing of this section of Crowhill Road once we have confirmed that all Scottish Water sewer repairs are finished.
- Angus Ave, Quarter 1, Date Completed 11/07/2025
- Kenmure Lane, Quarter 3,
- Lenzie Road, Quarter 2, Date Completed 08/09/2025, Comment: Anti Skids programmed for early October 25
- Regent SQ + Glenbank Rd, Quarter 2, Date Completed 28/08/2025, Comment: Regent SQ postponed due to finding coal tar
- Burnbrae Road, Quarter 3,
- Carron Crescent + Birken Rd, Quarter 3,
- Parkburn Avenue, Quarter 3,
- Laxton Drive + Orchard Brae, Quarter 4,
- Southbank Drive, Quarter 4,
- Kilsyth Road, Quarter 1, Date Completed 09/05/2025
- Redbrae Road, Quarter 1, Date Completed 27/06/2025
- Newdyke Road, Quarter 2, Date Completed 18/07/2025
- Main St- Twechar, Quarter 2, Date Completed 05/09/2025
- The under noted accordion shows the 2025/26 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.
Footway Resurfacing 2025/26 completed by internal resources
- Rosslynn Road, Quarter 1, Date Completed 04/08/2025, Comment: From Castlehill School to Dryburgh Road on both sides. The footway resurfacing, originally scheduled for next year has been brought forward to this year and will replace the previously planned works on Gallowhill Road. This change was made due to a conflict with utility works affecting Gallowhill Road, which has now been postponed to next year- Only one side resurfaced due to resources issue
- Milngavie Road (phase 2), Quarter 2, Date Completed 30/09/2025, Comment: Mosshead to Manse-House side only
- Inveroran Drive, Quarter 1, Date Completed 15/05/2025,
- Milngavie road, Quarter 1, Date Completed 22/05/2025, Comment: MacFarlane mini-roundabout to Kessington shop- one side only
- Drymen Road, Quarter 2, Date Completed 05/08/2025, Comment: Station Road to Cross
- Auchinairn Road, Quarter 4
- Fellsview Avenue, Quarter 3
- Alexander Place, Quarter 3
- Park St, Quarter 3
- Gallowhill Road, Quarter 1, Postponed to next year: The footway resurfacing originally scheduled for this year has been postponed to next year and replaced with Rosslynn. This change was made due to a conflict with utility works affecting Gallowhill Road.
- Boghead Road, Quarter 2, Abandoned: Postponed due to conflict with utility company
- Craigenbay Road, Quarter 4,
- At this stage, there are no carriageway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.
- At this stage, there are no Footway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.
- In summary, the Service is commencing the year with the aspiration to complete the 47 carriageway and 11 footway locations listed but will add others if additional external resources can be secured during the financial year.