Technical Notes 2023, Issue 75 - Roads & Environment 2023/24 Carriageway and Footway Resurfacing Programme

Report by: 
Ann Davie, Depute Chief Executive
TN Number: 
075-23
Subject: 
Roads & Environment 2023/24 Carriageway and Footway Resurfacing Programme
Responsible Officer: 
Thomas McMenamin, Executive Officer – Roads & Environment
Publication: 
This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.
Details: 
  1. The purpose of the Technical Note is to provide Members with an overview of the 2023/24 Roads & Environment Carriageway and Footway Resurfacing Programme.
  1. The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.
  1. In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
  1. All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
  1. The Service will provide a further quarterly progress update via Technical Notes in July 23, October 23, and January 24 along with a final update in March 24.
  1. The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
  1. Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
  1. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by internal resources working on non-coal tar locations as part of core capital works.
     
    Council Ward Carriageway Resurfacing 2023/24 Quarter Date Completed

    Milngavie

    Craigielea Crescent Internal resour2es 2  
    Ashburn Road Internal resources 2  
    Craigton Avenue (phase 1) Internal resources 2  
    Craigton Road Internal resources 3  
    Craigton Avenue (phase 2) Internal resources 3  
    Glasgow Road Internal resources 3  
    Vivian Avenue Internal resources 4  
    Breadie Drive Internal resources 4  

    Bearsden North

    Westbourne Crescent (phase 1) Internal resources 1  
    Wyvis Avenue Internal resources 1  
    Drymen Road (starts at Stockiemuir Road) Internal resources 2  
    Lawers Drive Internal resources 2  
    Cairngorm Crescent Internal resources 2  
    Craigmore Road (phase 1) Internal resources 2  
    Pentland Place Internal resources 2  
    Baljaffray Road Internal resources 3  
    Westbourne Crescent (phase 2) Internal resources 4  
    Craigmore Road (phase 2) Internal resources 4  

    Bearsden South

    Milngavie Road (Hillfoot) phase 1 Internal resources 1 April 2023
    Milngavie Road (Hillfoot) phase 2 Internal resources 1 April 2023
    Durness Avenue (phase 1) Internal resources 1  
    Glenfarg Crescent Internal resources 1  
    Tweed Drive Internal resources 1  
    Durness Avenue (phase 2) Internal resources 4  
    Chester Road Internal resources 4  

    Bishopbriggs North & Campsie

    Charlotte Avenue Internal resources 1 April 2023
    Birnam Avenue Internal resources 1 April 2023
    Glenorchard Road Internal resources 1  
    Birdston Road Internal resources 1  
    Laburnum Drive (phase 1) Internal resources 1  
    Crow Road Internal resources 1  
    Wester Cleddens Road Internal resources 2  
    Westfields Internal resources 2  
    Meadowburn Internal resources 3  
    Balmuildy Road Internal resources 3  
    Westerhill Road Internal resources 4  
    Laburnum Drive (phase 2) Internal resources 4  

    Bishopbriggs South

    Angus Avenue Internal resources 1 April 2023
    Huntershill Road Internal resources 1  
    Gannochy Drive Internal resources 2  
    Avon Road Internal resources 3  
    Muirpark Drive Internal resources 3  
    Ness Gardens Internal resources 4  
    Maree Gardens Internal resources 4  
    Lochy Gardens Internal resources 4  
    Rannoch Gardens Internal resources 4  
    Katrine Avenue Internal resources 4  

    Lenzie & Kirkintilloch South

    Heather Drive Internal resources TBC  

    Kirkintilloch East & North Twechar

    David Gray Drive Internal resources 1 April 2023
    New Dyke Avenue Internal resources 1  
    Peel Park Roundabout (phase 1) Internal resources 1  
    Main Street, Twechar Internal resources 2  
    Peel Park Roundabout (phase 2) Internal resources 2  
    Langmuir Road (phase 1) Internal resources 2  
    Campsie Road Internal resources 3  
    Waterside Road Roundabout (phase 1) Internal resources 3  
    Waterside Road Roundabout (phase 2) Internal resources 3  
    Langmuir Road (phase 2) Internal resources 4  


     

  2. The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by internal resources working on non-Coal Tar locations as part of the core capital works
     

    Council Ward

    Footway Resurfacing 2023/24

    Quarter

    Date Completed

    Milngavie

    Vivian Avenue

    Internal resources

    1

    April 2023

    Crossburn Avenue

    Internal resources

    1

     

    FIndlay Rise

    Internal resources

    2

     

    Hilton Road

    Internal resources

    2

     

    Kelvin Road

    Internal resources

    3

     

    Station Road

    Internal resources

    4

     

    South Mains Road

    Internal resources

    TBC

     

    Bearsden South

     

    Ballater Drive

    Internal resources

    3

     

    Bishopbriggs North & Campsie

    Lochiel Drive

    Internal resources

    1

     

    Allander Gardens

    Internal resources

    1

     

    Meadowburn

    Internal resources

    2

     

    Teviot Avenue

    Internal resources

    2

     

    Lochalsh Crescent

    Internal resources

    3

     

    Kirkintilloch Road (phase 1)

    Internal resources

    3

     

    Kirkintilloch Road

    Internal resources

    3

     

    School Road

    Internal resources

    TBC

     

    Kirkintilloch Road (phase 2)

    Internal resources

    TBC

     

    6. Lenzie & Kirkintilloch South

     

    Gallowhill Road

    Internal resources

    4

     

    7. Kirkintilloch East & North Twechar

     

    New Dyke Avenue

    Internal resources

    1

     

    Langmuir Avenue

    Internal resources

    4

     


     

  3. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on coal tar locations as part of core capital works.
     

    Council Ward

    Carriageway Resurfacing 2023/24

    Quarter

    Date Completed

    Milngavie

    Connell Crescent

    External resources

    TBC

    TBC

    Dougalston Avenue

    External resources

    TBC

    TBC

    McGrigor Avenue

    External resources

    TBC

    TBC

    Blackwood Avenue

    External resources

    TBC

    TBC

    Clobber Road

    External resources

    TBC

    TBC

    Bearsden North

     

    Huntershill Ave

    External resources

    TBC

    TBC

    Bishopbriggs South

     

    Coltpark Ave

    External resources

    TBC

    TBC

    Lenzie & Kirkintilloch South

     

    Gallowhill Ave

    External resource

    TBC

    TBC

    Kirkintilloch East & North Twechar

     

     

     

    Lithgow Ave

    External resources

    TBC

    TBC


     

  4. The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by external resources working on coal tar locations.
     

    Council Ward

    Footway Resurfacing 2023/24

    Quarter

    Date Completed

    Bishopbriggs South

    Coltpark Ave

    External resources

    TBC

    TBC

  5. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on non-coal tar locations.
     

    Council Ward

    Carriageway Resurfacing 2023/24

    Quarter

    Date Completed

    Milngavie

    B8050 Craigdhu Rd (Ferguson & Crossburn Ave junction)

    External resources

    TBC

     

    Bishopbriggs North & Campsie

     

    A891 at Junction with Campsie Road

    External resources

    TBC

     

    Main Street (Torrance)

    External resources

    TBC

     

    Torrance Road (A807) at junction of A803 & Canal bridge)

    External resources

    TBC

     

    Bishopbriggs South

     

    Cadder Road (phase 2)

     

    1

    April 2023

    Springfield Road (one way section)

     

    2

     

    Kirkintilloch East & North Twechar

     

     

     

    Waterside Road (B8048 gateway section)

    External resources

    TBC

     


     

  6. The under noted table shows the locations selected as part of the Additional Capital funding originally awarded to Roads & Environment Service in 2022/23. Regrettably, these locations were not progressed as part of the 2022/23 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works.
     

    Council Ward

    Footway Resurfacing 2023/24

    Quarter

    Date Completed

    Milngavie

    Dougalston Avenue

    2023/24

    TBC

     

    Drumcarn Drive

    2023/24

    TBC

     

    Bearsden North

    Milngavie Road (Westside near Mosshead Road)

    2023/24

    TBC

     

    Ravelston Road

    2023/24

    TBC

     

    Bearsden South

    Killermont Road

    2023/24

    TBC

     

    Maxwell Avenue

    2023/24

    TBC

     

    Bishopbriggs North & Campsie

    Allander Gardens

    2023/24

    TBC

     

    Teviot Avenue

    2023/24

    TBC

     

    Cander Rigg

    2023/24

    TBC

     

    School Road

    2023/24

    TBC

     

    5, 7 & 9 Moray Drive

    2023/24

    TBC

     

    Bishopbriggs South

     

    Springfield Square (at western end)

    2023/24

    TBC

     

    Kirkintilloch East & North Twechar

    Alexander Place

    2023/24

    TBC

     

    Briar Road

    2023/24

    TBC

     

  7. The Service is in the process of renewing the contract to utilise an appointed external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the procurement process the tables within sections 10, 11, 12 and 13 will be updated later in the year.
     
  8. In summary, the Service is commencing the year with the aspiration to complete the 73 carriageway and 35 footway locations listed, but will add others if additional external resources can be secure during the financial year.
Distribution List: 