Report by:
Ann Davie, Depute Chief Executive
TN Number:
054-23
Friday, 31 March, 2023
Subject:
Bearsden & Milngavie PS Projects – Easter Surveys
Responsible Officer:
Alan Bauer, Executive Officer - Assets & Facilities
Publication:
This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared outwith the Council.
Details:
- The purpose of this technical note is to advise members that in support of development of proposals for the refurbishment of Bearsden and Milngavie Primary Schools, a series of pre-construction site investigations are planned to be undertaken over the course of the Easter holidays.
- Surveys will include:
Bearsden Academy: commencing 3rd April for 2 days, x7 trial pit excavations around the sports pitch to support the development of the design for the Bearsden PS decant school.
Bearsden Primary School: commencing 5th April for 3 days, x3 boreholes and x2 trial pits to support the development of design proposals for the refurbishment of the school.
Milngavie Primary School: commencing 10th April for x3 days, x8 boreholes and x3 trial pits to support the development of design proposals for the refurbishment of the school
- Each site will be fully reinstated to their original condition on completion of the surveys and all works will be cleared prior to the re-opening of each school after the Easter break.