Technical Notes 2022, Issue 07 - Roads & Environment 2021/22 Carriageway and Footway Resurfacing Programme Quarterly Update

Report by: 
Ann Davie, Depute Chief Executive
TN Number: 
007-22
Subject: 
Roads & Environment 2021/22 Carriageway and Footway Resurfacing Programme Quarterly Update
Responsible Officer: 
Thomas McMenamin, Executive Officer - Roads & Environment
Publication: 
This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared outwith the Council.
Details: 
  1. The purpose of the technical note is to provide Members with an update on the previous quarters Roads & Environment 2021/22 Carriageway and Footway Resurfacing Programme.
     
  2. As a result of restrictions placed on the service in relation to single person vehicle occupancy and social distancing the Roads Network Team were initially delayed in commencing the resurfacing programme for 2021/22.
     
  3. Through the introduction of vehicle screens and the amendment of safe working practices the Roads Network Team were able to return to carriageway resurfacing operations on 7th June 2021.
     
  4. Since June 2021, the team were able to complete resurfacing below listed carriageways:
     
    Council Ward Carriageway Resurfacing 2021/22 Quarter Date completed
    Kirkintilloch East & North Twechar Shirva Road 1 18/06/21
    Lenzie & Kirkintilloch South Easter Garngaber Road 1 25/06/21
    Bishopbriggs South Lennox Crescent Phase 1 1 02/07/21
    Kirkintilloch East & North Twechar Newdyke Road 2 06/07/21
    Bearsden South Switchback Road 2 16/07/21
    Lenzie & Kirkintilloch South Auchinloch Road 2 23/07/21
    Bishopbriggs North  & Campsie  Birdston Road 2 06/08/21
    Bishopbriggs North  & Campsie  Balmuildy Road 2 27/08/21
    Bearsden South Canniesburn Road 2 03/09/21
    Milngavie Stockiemuir Road 2 10/09/21
    Milngavie Balvie Road 2 18/09/21
    Kirkintilloch East & North Twechar Union Street 2 24/09/21
    Bearsden South Speirs Road (Phase 1) 3 08/10/21
    Milngavie Station Road 3 15/10/21
    Bearsden North Montrose Drive 3 22/10/.21
    Bishopbriggs South Lennox Crescent Phase 1 3 29/10/21
    Bearsden North Loyal Gardens 3 05/11/21
    Bishopbriggs North  & Campsie Cadder Road 3 12/11/21
    Bishopbriggs South Auchinairn Road 3 19/11/21
    Bishopbriggs North  & Campsie  Birkhill Avenue 3 26/11/21
    Milngavie North Dumgoyne Ave 3 03/12/21
    Milngavie Mosspark Road 3 10/12/21
    Bearsden South Larchfield Road 3 17/12/21
    Milngavie Cloberfield Gardens 3 23/12/21


     

  5. List programmed for carriageway resurfacing in current quarter:
     
    Council Ward Carriageway Resurfacing 2021/22 Quarter Aim start date
    Lenzie & Kirkintilloch South Mill Way 4 10/01/22
    Lenzie & Kirkintilloch South Duntiblae Road 4 12/01/22
    Bearsden South Killermont Road 4 17/01/22
    Milngavie Hunter Roundabout 4 05/02/22
    Bishopbriggs South Torr Road 4 14/02/22
    Bishopbriggs North  & Campsie Glenburn Gardens 4 21/02/22
    Milngavie Bleachfield 4 28/02/22
    Milngavie Buchanan Drive 4 TBC
    Milngavie Auchenhowie Rd 4 21/03/22


     

  6. The following lists of carriageways contaminated with coal tar which will be programmed for carriageway resurfacing in the current quarter by an external contractor :
     
    Council Ward Carriageway Resurfacing 2021/22 Quarter Aim start date
    Lenzie & Kirkintilloch South Almond Drive 4 TBC
    Bearsden South Woodvale Avenue 4 TBC
    Milngavie Blane Drive 4 TBC
    Milngavie Roselea Drive 4 TBC
    Bishopbriggs South Muirpark Drive 4 TBC
    Milngavie Buchanan Street 4 TBC


     

  7. The following lists footways contaminated with coal tar which will be programmed for footway resurfacing in the current quarter by an external contractor :
     
    Council Ward Footway Resurfacing 2021/22 Quarter Aim start date
    Bishopbriggs South Flora Gardens 4 TBC
    Bishopbriggs South Eileen Gardens 4 TBC
    Bishopbriggs South Elspeth Gardens 4 TBC


     

  8. Unfortunately, the following works previously programmed were unable to be completed due to Covid restrictions affecting resources on the scheduled dates.  The service is committed to rescheduling the programme to delivering these projects within the financial year and projects will be reprogrammed as resources become available over the course of the upcoming year.
     
    Council Ward Carriageway Resurfacing 2021/22 Quarter Aim start date
    Bishopbriggs South Springfield Road TBC TBC
    Bishopbriggs South Kirkintilloch Road TBC TBC
    Milngavie B8050 Craigdhu Road TBC TBC
    Lenzie & Kirkintilloch South Emerson Road West TBC TBC
    Lenzie & Kirkintilloch South Boghead Road TBC TBC


     

  9. Unfortunately, Footway resurfacing action is still on hold due to difficulties with Covid restrictions.  The footway projects will be reprogrammed as resources become available over the course of the upcoming year.