LDP2 Action Programme

Introduction

Section 21 of the Planning etc. (Scotland) Act 2006 (“The Act”) requires planning authorities to prepare an Action Programme setting out how the authority proposes to implement their Local Development Plan (LDP). The Planning (Scotland) Act 2019 subsequently amended Section 21 so that Action Programmes are now known as Delivery Programmes. However, as the LDP2 has been prepared under the 2006 Act, it will continue to be referred to as an ‘Action Programme’. This Action Programme therefore accompanies the East Dunbartonshire Local Development Plan 2 in accordance with The Planning etc (Scotland) Act 2006. Under Planning Regulations, the finalised Action Programme must be adopted and published by the Council within three months of the adoption of the Local Development Plan 2.

On this page you will find information on:

Purpose

The Action Programme is intended to help align the delivery of the Local Development Plan 2 with corporate and national investment in infrastructure. It will be used by the Council as a delivery mechanism to deliver the best possible outcome for the area and to co-ordinate development proposals with the infrastructure and services needed to support them.

This Action Programme has the following purpose:

  • It sets out a detailed plan of actions needed to deliver the key infrastructure, proposed development sites and policies set out in the Plan;
  • It acts as a project management tool for coordinating the partnership working required to deliver the Plan by a range of organisations;
  • It provides an understanding the likely costs of delivering the Plan and coordinating funding sources; and
  • It is a mechanism for monitoring whether commitments are being met.

Specific site requirements and expectations are not repeated within this Action Programme. Instead, it focuses on the key actions that are required to deliver each site and implement each policy included within LDP2.

Understanding the Action Programme

Section 1 – Development Strategy – This section provides details of how the Council expects each individual aspect of the Development Strategy to be delivered.

Section 2 - Community Areas – The LDP 2 groups East Dunbartonshire into seven ‘community areas’ to reflect local geographies and community requirements. The Community Policy for each area provides a detailed development strategy and development priorities. This section of the Action Programme provides an overview of the key projects and infrastructure requirements within each area, together with a summary of how these are expected to be delivered. It also identifies local site specific designations, features and land use proposals or projects. The ‘progress’ column within these tables will be updated at each monitoring stage, where required.

Section 3 - Subject Policies – The Plan contains 16 ‘subject policies’ which will be used to assess planning applications. These are categorised into overall policies applicable to all applications, specific policies which relate to a certain land use or type of proposal, general safeguarding and protection policies which apply when a proposal has a particular site specific consideration or opportunity, and a policy setting out developer contribution requirements. This section of the Action Programme provides an overview of how these should be implemented. The ‘progress’ column within these tables will be updated at each monitoring stage, where required.

Delivery Partners

Collaboration between the private and public sectors is needed to deliver development, planned infrastructure and services throughout our communities. This will be supported by guidance and advice provided by key agencies and other regulatory organisations. Joint working and action between a wide range of partners will therefore be essential in delivering the spatial strategy, policies and proposals within the Plan. This includes landowners, developers, key agencies, community groups and other public sector organisations.

In some cases, developer contributions will be sought to achieve sustainable growth and development, as set out in Policy 24. In addition, the funding of many proposals contained within the Action Programme will be dependent on future Scottish Government spending reviews and the availability of public and private sector finance such as government infrastructure funding.

The Council will also work closely with our neighbouring authorities through the City Region, Clydeplan and other regional partners to ensure that opportunities for economic growth and the creation of sustainable patterns of development and infrastructure needs are planned for collaboratively across boundaries.

Monitoring

The delivery of sites and development can often be complex and in many cases subject to delay or slippage as a result of both internal and external factors. The Action Programme therefore needs to be flexible in response to change, proposing alternative solutions when needed (so long as these are consistent with the Development Plan) and assessing the impact of any change on remaining proposals. Governance arrangements will be put in place to ensure progress is sufficiently monitored and that actions are taken forward by the relevant organisations within a reasonable timescale.

The Council is required to review and republished the Action Programme at least every two years. This will allow the Council to provide updates on the progress of actions and review the format where required. On publication, it will be available on-line and copies will be sent to Scottish Ministers.

If you have and questions about this Action Programme, please contact the Land Planning Policy team by email at development.plan@eastdunbarton.gov.uk or by telephone via 0345 123 4510 (Customer Services).

Section 1 - Development Strategy (Policy 1)

The following table provides details of how the key elements of the development strategy will be delivered by the end of the LDP 2 period (2027).

Key Elements

Action

Responsibility /

Delivery Partner(s)

Progress

Direct development to brownfield sites in the urban area and the key areas of change

Monitor vacant and derelict land annually

EDC

Ongoing. Data for 2021- 22 submitted to Scottish Government in September 2022. The Council is also working directly with the Glasgow City Region team to explore issues around remediation and the reduction in VDL sites in general.

Prepare brownfield land strategy and planning guidance

EDC

Updated Brownfield Land Planning Guidance published September 2022. Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023.

Develop allocated housing sites

Engage with house builders and work proactively to bring forward and commit to the development of the sites that they have promoted for inclusion

within the plan.

Landowners and developers (further details contained within community area sections)

EDC

Sites agreed through examination and LDP2 published in November 2022. Work to deliver sites is ongoing.

 

Key Elements

Action

Responsibility /

Delivery Partner(s)

Progress

Support the vitality and viability of town and village centres and the regeneration of the Place Plan areas

Continue to implement adopted town centre strategies

EDC, local businesses, community groups

Significant progress has been made on all 3 TCSs. In Bearsden, accessibility enhancements are being taken forward via the Active Travel Strategy 2. Redevelopment of Brookwood Villa underway following successful funding bid. Due for completion in 2023. In Bishopbriggs, redevelopment of the former High School site is underway and work related to public realm enhancements as part of the City Deal Place and Growth Programme is ongoing. In Milngavie, a wide range of public realm and improvements to the business environment have already been achieved via the Milngavie BID team and local community groups. See relevant community area policies and Policy 14 for more information.

Develop town centre strategy for Kirkintilloch

EDC, local businesses, community groups

A range of physical and non-physical initiatives continue to be developed and delivered under the existing town centre strategy for Kirkintilloch (The Kirkintilloch Town Centre Masterplan), also informed by more recent community lead engagement. – see Policy 4 for more information.

 

Key Elements

Action

Responsibility /

Delivery Partner(s)

Progress

 

 

Promote and implement Local Place Plans Work with landowners to manage peatland for carbon mitigation and biodiversity, including Lenzie Moss, High and Low Moss, Campsie Fells and Barbeth Moss. Manage woodlands to encourage recreational access and biodiversity. Establish appropriate solutions to the problems associated with disused land, poor quality green space, upland areas and fragmented habitats, though the Glasgow and the Clyde Valley Green Network Partnership.

EDC, community groups

The Council is undertaking early preparatory work, including a revised Development Plan Scheme and Participation Statement, which will address the role of LPPs. Further engagement with local communities will take place in 2023.

 

Protect, enhance and expand the green network

  • Landowners & developers
  • SNH
  • Scottish Forestry
  • Woodland Trust

Ongoing

 

 
 
  • Landowners &

Clydeplan Forestry and Woodland Strategy published in December 2020. The Council is also engaging with Scottish Forestry in relation to a Long Term Forest Plan for Lennox Forest.

 

developers

  • EDC
  • Scottish Forestry
  • Woodland Trust

Ongoing

 

 

 

 

 

 

 

 

 
 
 
 
 
  • GCV Green Network Partnership
  • EDC
 
 
 

Section 2 - Community Area

Policy 2 - Bearsden Community Area

Map – Council projects identified in the Bearsden Community Policy in LDP2 (Policy 2.CF)

Map – Council projects identified in the Bearsden Community Policy in LDP2 (Policy 2.CF)

Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions & Delivery Requirements

Responsibility/ Delivery Partner(s)

Target Delivery Date

Progress

Bearsden Town Centre

 

  • Undertake health check every two years
  • Continue to implement town centre strategy
  • Work with delivery partners to establish any emerging issues
  • Monitor development activity via planning applications
  • Ensure implementation of town centre first principle

EDC

Local Traders Group and other businesses

 

2027

 

Town centre strategy in place (2018). Work towards enhanced accessibility via Active Travel Strategy 2 underway. Evidence base established and report due to be presented to Committee in Jan 2023. Redevelopment of Brookwood Villa underway following successful funding bid. Due for completion in 2023.

 

 

 

Site Name / Theme

Actions & Delivery Requirements

Responsibility/ Delivery Partner(s)

Target Delivery Date

Progress

Local Centres (Baljaffray.

Bearsden Station, Canniesburn, Kessington, Hillfoot)

Protect function of all centres by ensuring adherence to sequential test approach

EDC

2027

The Council is maintaining strong protection of local centres via the development management process for relevant planning applications.

2.BE1

Canniesburn Gate

Continue to protect the role and function of this fully occupied

site.

Current occupiers

2027

Ongoing

2.BE2

Garscadden Depot

Determination of planning permission

Site developer

2027

Site has been disposed and Council is awaiting planning application.

2.BE3 Garscube Estate

Establish potential for site use and/or intensification as part of future brownfield land strategy

Glasgow City Council

City Deal Project team

Current occupiers

2027

Wider site (West of Scotland Science Park, Glasgow) currently identified as a Strategic Economic Investment Location.

Antonine Wall World Heritage Site

Publish and promote updated Supplementary Guidance

Antonine Wall Protection Group

2023

Council is currently liaising with other member Councils on finalising the guidance ahead of publication. East Dunbartonshire  Council consulted on the draft Guidance in 2022.

 

Site Name / Theme

Actions & Delivery Requirements

Responsibility/ Delivery Partner(s)

Target Delivery Date

Progress

2.H1 Bearsden Golf Course

Monitor development

of site in line with planning consent

Site developer

2024

Under construction

2.H2 Castlehill Farm

Monitor development

of site in line with planning consent

Site developer

2023

Under construction

2.H3 Drymen

Road

None

EDC

Site developer

2021

Complete

2.H4 Crarae Avenue

Engage with site owner to bring forward site.

EDC

Site developer

2021

Engagement to take place as part of Housing Land Audit 2023.

2.H5 Kilmardinny

Engage with site owner/ developer and work proactively to bring forward the remaining development of the site.

Site developer

2022

Majority of site now complete. Only remaining area to the south remains undeveloped – expected to be delivered within lifespan of Plan.

2.H6 190-196

Milngavie Road

Engage with site owner/ developer and work proactively to bring forward the development of the

site.

Site developer

2027

Land owner expects development to come forward later in plan period

2.H7 Netherton

Farm Lane

Monitor site

construction

EDC

Site developer

2022

Under construction

2.H8 Nithsdale Crescent

Determination of planning permission

EDC

2022

A recent CPO by the Council was unsuccessful. The Council is now undertaking additional feasibility work with the aim of being in a position to determine alternative options by April 2023.

Policy 3 - Bishopbriggs Community Area

Map – Council projects identified in the Bishopbriggs Community Policy in LDP2 (Policy 3.CF)

map showing Council projects identified in the Bishopbriggs Community Policy in LDP2 (Policy 3.CF)

Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions

Responsibility/ Delivery Partner(s)

Target Delivery Date

Progress

Auchinairn Place Plan

Support implementation of the Place Plan including:

  • 3 areas of priority: affordable activities for all; healthy and safe outdoors; and informed choices and growing capacity
  • 7 land use projects

EDC

2024

Place Plan runs from 2019-2024.

Bishopbriggs Town Centre

  • Undertake health check every two years
  • Continue to implement strategy
  • Work with delivery partners to establish any emerging issues
  • Monitor development activity via planning applications
  • Ensure implementation of town centre first principle

EDC

2027

The Council’s City Deal projects – the East Dunbartonshire Place and Growth Programme – will support the delivery of the town centre strategy. This includes a Public Realm Plan and development of the former Bishopbriggs High School Site. The Council also conducted a consultation on potential new business space in Spring 2022.

 Auchinairn Local Centre

Protect function of centre by ensuring adherence to sequential test approach

 EDC

2027

Ongoing

Strathkelvin Retail Park

  • Undertake annual review of unit occupiers
  • Safeguard for comparison retail

 EDC 

 2027

 Ongoing

Westerhill Regeneration Area

  • Preparation of Masterplan
  • Progress City Deal Place and Growth Programme

 Site developers EDC

 2027

All aspects are ongoing as part of the City Deal Place and Growth Programme.

3.BE2 Bishopbriggs Industrial Estate

Establish potential for vacant site use and/or intensification

 EDC Site developers

2027

Vacant and Derelict Land audit and storymap to be published early 2023.

3.BE6 Low Moss Industrial Estate

Monitor development of site in line with planning consent

EDC Site developer

2027

 Under construction

3.BE8 Westerhill Industrial Estate

  • Preparation of masterplan
  • Progress City Deal Place and Growth Programme

 Site developers EDC

2027

Ongoing as part of the City Deal Place and Growth Programme

3.H1 Auchinairn Primary School, Former, Beech Road

Submit planning application and progress through development management process

Site developer EDC

2026

Future action

3.H2 Bishopbriggs Town Centre/ Former High School

Monitor site construction

Site developer EDC

2027

Under construction

3.H3 Cadder Sewage Works/Jellyhill

Monitor site construction

Site Developer EDC

2024

Under construction

3.H4 St Mungo Street

None

EDC

2022

Complete

3.H5 Westerhill Regeneration Area

  • Preparation of Masterplan
  • Support City Deal process

Site developers EDC

2032

Ongoing as part of the City Deal Place and Growth Programme.

3.BR1 Barrage Balloon Site

Part of Westerhill Regeneration Area – see 3.H5

3.H5

2027

Ongoing as part of the City Deal Place and Growth Programme.

3.BR3 Crofthead Quarry

Establish green network enhancement opportunity for grassland, woodland 

Undertake ground Investigation due to former landfill use.

EDC Site owner

2027

Site is designated as a Green Network node and Open Space, LNCS and Habitat Link in LDP2. Value and potential of site will also be explored via Greenspace Strategy in 2023.

3.BR4 Low Moss Industrial Estate

See 3.BE6

 

2027

Under construction (data centre)

3.BR5 Meadowburn, Former Quarry

Establish green network enhancement opportunity – woodland and  grassland.

Undertake ground Investigation, due to former quarry use.

 

2027

Site continues to be recorded on VDL register. Audit scheduled for publication late 2022.

3.BR6 Westerhill Road, Former Oil Terminal

See 3.H5

 

2027

Ongoing as part of the City Deal Place and Growth Programme.

3.BR7 Westerhill Road South

See 3.H5

 

2027

Ongoing as part of the City Deal Place and Growth Programme.

Policy 4 - Kirkintilloch, Lenzie and Waterside Community Area

Map – Council projects identified in the Kirkintilloch, Lenzie and Waterside Community Policy in LDP2 (Policy 4.CF)

map showing council projects identified in the Kirkintilloch, Lenzie and Waterside Community Policy in LDP2 (Policy 4.CF)Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions

Responsibility/ Delivery Partner(s)

Target

Delivery Date

Progress

Hillhead and

Harestanes Place Plan

Support

implementation of projects identified

Local Community EDC

2023

Place Plan runs from 2018-2023

Kirkintilloch Town Centre

  • Prepare Town Centre Strategy Undertake health check every two years
  • Work with delivery partners to establish any emerging issues
  • EDC
  • Local Businesses and retailers
  • Kirkintilloch Community Council
  • Other community groups

2027

Delivery of the Kirkintilloch Town Centre Masterplan continues with The Council’s current activities focused on the redevelopment of Regent’s Gardens. Projects have been delivered by Kirkintilloch Community Council (Your Kirky) such as the Townhead Square project. The development of a town centre strategy for Kirkintilloch will be considered with the community as part of developing LDP3.

Local Centres (Lenzie, Merkland and Millersneuk)

Protect function of centre by ensuring adherence to sequential test approach

EDC 

2027

Ongoing

4.BE5 Kirkintilloch Industrial Estate East

Establish potential for vacant site use and/or intensification as part of future brownfield land strategy

EDC Site developers

2027

Ongoing

4.BE6 Milton Road

Establish potential for vacant site use as part of future brownfield land strategy

EDC Site developers

2027

Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023.

4.BE7 Pit Road

Establish feasibility of improving access to site and overall condition of site

EDC Site owners

2027

To be undertaken within lifespan of the Plan

4.BE10 Southbank Works

Establish potential for vacant site use as part of future brownfield land strategy

EDC Site developers

2027

Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023.

4.BE11 Woodilee Industrial Estate

Establish potential for vacant site use as part of future masterplan

EDC Site developers

2027

The Masterplan was completed in 2022. Planning consents are now being brought forward on the site

4.H1 Armour Drive Lock Ups

None

EDC 

2021

Complete

  

4.H2 Blackthorn Grove Lock Ups (Lenzie)

 None

 EDC

 2021

 Complete

4. H3 Braes O'Yetts

  None

  Site developer

 2022

 Complete

 

4.H4 Broomhill Hospital

 Monitor site construction

Site developer EDC

2024

Under construction

4.H5 Campsie View School

Submit planning application

Site developer/EDC

2032

Future action

4.H6 Claddens South/ Blackland Place

Monitor site construction

Site developer EDC

2022

Under construction

4.H7 Cleddans Playing Field

Submit refreshed planning application

EDC 

2023

Future action

4.H8 David Gray Drive/ Fossil Grove

None

EDC 

2027

Complete

4.H9 Duntiblae

Engage with site owner/ developer and work proactively to bring forward the development of the site.

Site developer EDC

2025

Future action

4.H10 Fauldhead/ Chryston Road North

Conclude legal agreement and fulfil pre-start conditions.

Site developer EDC

2025

Planning application granted subject to conclusion of legal agreement

4.H11 Fauldhead/Chryston Road South

Conclude legal agreement and fulfil pre-start conditions.

Site developer EDC

2025

Planning application granted subject to conclusion of legal agreement

4.H12 Glasgow Rd

Submit planning application

EDC 

2023

Future action

4.H13 High Street/ Mitchell Hire

Monitor site construction

Site developer EDC

2022

Under construction

4.H14 38 Kilsyth Road

None

 

RSL

2023

Complete

4.H15 Kirkintilloch Gateway Regeneration Area

Engage with site owner/ developer and work proactively to bring forward and commit to the development of the site as part of masterplan.

 Site owners EDC

 2032

The Masterplan was completed in 2022. Planning consents are now being brought forward on the site.

Class 1 retail store disposed to grant subject to conditions and S75 legal agreement. Legal negotiations are progressing and decision notice anticipated early 2023.

4.H16 Lairdsland School

Monitor site construction

 EDC

 2022

Under construction, completion anticipated March 2023

4,H17 Lenzie Primary, former

Monitor site construction

Site developer EDC

 2021

 Under construction

4.H18 Meadowburn Avenue

Engage with site owner/ developer and work proactively to bring forward the site.

 Site developer EDC

 2027

 Ongoing

4.H19 Merkland School

Submit planning application

Site Developer/EDC

 2032

 Ongoing

4.H20 Moss Road

Submit planning application

 EDC

 2027

 Ongoing

4.H21 Redbrae Road/ Oxgang Holdings

Conclude renegotiated legal agreement and recommence works on site

 Site developer EDC

 2022

Ongoing legal procedures due to liquidation of previous developer

4.H22 Rob Roy Football Club Phase 2

 Monitor site construction

 Site developer

 2023

Under construction, completion anticipated Jan 2023

4.H23 St Agatha’s Primary, former

 Monitor site construction

 EDC 

 2022

 Complete

4.H24 Tom Johnston House, former

 None

 EDC 

 2022

 Complete

4.H25 Townhead (85 – 97)

 None

 RSL

 2021

 Complete

4.H26 Whitegates

 Monitor site construction

Site developer EDC

 2027

 Under construction

4.BR9 Waterside Bing

Engage with site owner and work proactively to bring forward required site use (biodiversity green network enhancements)

EDC Landowner

 2027

 Further action

Policy 5 - Lennoxtown, Milton of Campsie, Haughhead and Clachan of Campsie Community Area

Map – Council projects identified in the Lennoxtown, Milton of Campsie, Haughhead and Clachan of Campsie Community Policy in LDP2 (Policy 5.CF)

map showing Council projects identified in the Lennoxtown, Milton of Campsie, Haughhead and Clachan of Campsie Community Policy in LDP2 (Policy 5.CF)Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions

Responsibility/Delivery Partner(s)

Target Delivery Date

Progress

Lennoxtown Place Plan

  1. Rebalance the street towards pedestrian movement and activity
  2. Support cyclists
  3. Create a place which residents and tourists wish to visit
  4. Reduce vehicle speed through street design

EDC

Community

groups

2023

Currently being implemented.

 

 

 

Lennoxtown

Streetscene Project concept design refresh started for completion by end 22/23. Public consultation

underway.

Lennoxtown Village Centre

Protect function of centre by ensuring adherence to sequential test approach

EDC

2027

Ongoing

Milton of Campsie Village Centre

Protect function of centre by ensuring adherence to sequential test approach

 EDC 

 2027

 Ongoing

Lennoxtown Enterprise Centre

Market vacant units for office or appropriate employment use

 EDC

 2027

 Ongoing

5.H1 Baldoran House

 None

 EDC

 2021

 Complete

5.H2 Birdston Road

 None

 EDC 

 2022

 Complete

5.H3 Campsie Golf Club, Lennoxtown

Engage with site owner/ developer and work proactively to bring forward the site.

 Site developer EDC

 2027

 Future action

5.H4 East of Aldessan House

 Monitor site construction

 Site developer EDC

 2025

 Ongoing

 5.H5 Lennox Castle   Hospital

Engage with site owner/ developer and work proactively to bring forward the site.

 Site developer EDC

 2027

 Future action

5.H6 Lennoxlea, Lennoxtown

Engage with site owner/ developer and work proactively to bring forward the site.

 Site developer EDC

 2027

 Future action

 5.H7 Primrose Way

  • Determine demand for use as a Gypsy/ Travellers site through HNDA and LHS processes.
  • If demand observed submit planning application and deliver new facility.

 EDC

 2027

 Future action

5.H8 St Machan’s Way, Lennoxtown

 Submit planning application

 EDC 

 2027

 Future action

5.H9 Watshod Farm

 None

 Site developer

 2021

Complete

 Main Street

Establish opportunities for biodiversity  enhancement and green network improvements

 EDC

 2027

Lennoxtown Streetscene Project underway.

 5.BR1 Lennox Castle

Engage with site owner and work proactively to bring forward and commit to the development of the site for a suitable use.

EDC Site Owner

 2027

Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023.

5.BR2 Lennox  Castle Hospital

 See 5.H5

 

 2032

 See 5.H5

5.BR3 Main Street (rear of properties)

Engage with landowner to take forward required site uses (biodiversity)

Landowner EDC

 2027

Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023.

Policy 6 - Milngavie Community Area

Map – Council projects identified in the Milngavie Community Policy in LDP2 (Policy 6.CF)

map showing Council projects identified in the Milngavie Community Policy in LDP2 (Policy 6.CF)Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions

Responsibility/ Delivery

Partner(s)

Target Delivery

Date

Progress

Milngavie Town Centre

  • Undertake health check every two years
  • Continue to implement strategy
  • Work with delivery partners to establish any emerging issues
  • Monitor development activity via planning applications
  • Ensure implementation of town centre first principle
  • Milngavie BID
  • EDC
  • Local Businesses

2027

Ongoing. The Council is continuing to engage with and support Milngavie BID on delivering the business plan and in delivering the Town Centre Strategy. Public realm improvements delivered 2021 by Milngavie BID.

6.BE1 Cloberfield 
Industrial Estate

  • Monitor site construction
  • Update Business Land Audit

EDC Site owner

2027

There are a small number of vacant sites within the industrial estate and these are being recorded via the annual vacant and derelict land survey. Detailed VDL audit is due to be published in 2023.

6.H1 Bankell Farm

 None

 Site developer

 2021

 Complete

 6.H2 Craigton Rd

Engage with site owner/ developer and work proactively to bring forward development of the site.

 Site developer EDC

 2025

 Ongoing

6.H3 Drumclog Ave

Engage with site owner/ developer and work proactively to bring forward development of the site.

 Site developer EDC

 2027

 Ongoing

 6.H4 Keystone Road

 None

 EDC

 2021

 Complete

6.H5 Fire Station Field

 None

 Site developer

 2022

 Complete

6.H6 No 18 Strathblane Rd

 Fulfil pre-start conditions.

 Site developer EDC

 2025

Planning consent granted on appeal

6.BR3 Craigton Works

Engage with site owner/ developer and work proactively to bring forward and commit to the development of the site.

 Site developer

 2027

 Ongoing

Policy 7 - Torrance and Baldernock Community Area

Map – Council projects identified in the Torrance and Baldernock Community Policy in LDP2 (Policy 7.CF)

map showing Council projects identified in the Torrance and Baldernock Community Policy in LDP2 (Policy 7.CF)Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions

Responsibility/ Delivery Partner(s)

Target Delivery Date

Progress (note: column to be completed and updated prior to final publication)

Torrance Village Centre

Protect function of centre by ensuring adherence to sequential test approach

EDC

2027

Ongoing

7.H1 Acre Valley Nursery

Engage with site owner/ developer and work proactively to bring forward development of the site.

Site developer EDC

2027

Ongoing

7.H2 Balmore Garden Nursery

Determine planning application

Site developer EDC

2023

Planning application under consideration

7.H3 East of Ferrymill Motors

Engage with site owner/ developer and work proactively to bring forward

development of the site.

Site developer EDC

2027

Ongoing

7.H4 Kelvindale Nursery

Submit planning application

EDC

2027

Future action

7.H5 Kelvin View

Engage with site owner/ developer and work proactively to bring forward

development of the site.

Site developer RSL

EDC

2023

Ongoing

7.H6 Main Street (North)

None

EDC

2020

Complete

7.H7 Main Street (South)

Submit planning application

EDC

2025

Future action

Policy 8 - Twechar Community Area

Map – Council projects identified in the Twechar Community Policy in LDP2 (Policy 8.CF)

map showing Council projects identified in the Twechar Community Policy in LDP2 (Policy 8.CF)Table – Other key sites and proposed developments identified in LDP2

Site Name / Theme

Actions

Responsibility/ Delivery Partner(s)

Target Delivery Date

Progress

Twechar village centre

Protect function of centre by

ensuring adherence to sequential test approach

EDC

2027

Ongoing

Twechar Place Plan

Support implementation of projects identified

EDC

Local Community

2023

Place Plan runs from 2018-2023

8.BE1

Badenheath

Engage with site owner/ developer and work proactively to bring forward development of the site.

Undertake the following as a minimum:

  • Landscaping Plan
  • Active Travel Strategy
  • Ground Investigation
  • Noise Impact Assessment

Site developer EDC

2027

Ongoing

8.H1

Canalside (Barrhill Lodge and 1 Glen Shirva

Rd)

Engage with site owner/ developer and work proactively to bring forward development of the site.

Site developer EDC

2027

Ongoing

8.H2 Glen Shirva Rd Main Site

Engage with site owner/ developer and work proactively to bring forward

development of the site.

Site developer EDC

2027

Ongoing

8.H3

MacDonald Crescent

Engage with site owner/ developer and work proactively to bring forward

development of the site.

Site developer EDC

2032

Ongoing

8.BR2 Former Cemex Site (now

Breedon)

Establish potential for vacant site use

EDC

Site Owner

2027

Site is being evaluated as part of the VDL annual

survey 2022-23.

Section 3 - Subject Policies (9-24)

Policy Name

Actions

Responsibility/

Delivery Partner(s)

Timescales & Progress

9. Climate Change, Sustainability and Energy Infrastructure

Prepare and publish EDC Climate Action Plan

EDC

In progress, completion expected 2023

Prepare and publish Local

Heat and Energy Efficiency Strategy (LHEES)

EDC

In progress, completion expected 2023

Monitor use and implementation of Sustainability & Energy Statement Form as part of development management

process

EDC

Ongoing

10. Design and Placemaking

Review current Supplementary Guidance and update to reflect new sustainability standards and any other requirements.

EDC

Complete (August 2022)

Monitor implementation of Policy 10 through development management

process

EDC

Ongoing

11. Transport

Prepare and publish Sustainable Transport Planning Guidance

EDC

Complete (August 2022)

Deliver electric vehicle charging infrastructure in line with Electric Vehicle Action

Plan

EDC

Ongoing

Monitor air quality in Air Quality Management Areas in line with Local Air Quality

Management obligations

EDC

Ongoing

12. Housing

Undertake Housing Land Audit annually to ensure an effective 5 year supply is maintained

EDC

Ongoing

Monitor use of Policy 12

through development management process

EDC

Ongoing

13. Community Facilities and Open Space

Progress East Dunbartonshire

Council Major Projects

EDC

Ongoing

Publish new Open Space Strategy

EDC

In progress, completion expected in 2023

14. Network of Centres and Retailing

Ensure implement town centre first principle to all relevant applications

EDC

Ongoing

Monitor activity and occupancy at Strathkelvin Retail Park

EDC

Ongoing

15. Business and Employment

Deliver Economic Development Strategy and Produce Circular Economy Strategy

EDC and EDEP

In progress. Economic Recovery Plan published 2021.

16. Tourism

Encourage development of the visitor economy in line with Economic Development Strategy

EDC and EDEP

TBC

Deliver Economic Development Strategy

EDC and EDEP

Economic Recovery Plan published 2021. Delivery is ongoing with a number of actions being completed and underway. Those relevant to LDP2 such as projects in the Community section of the ERP have progress noted in this Action

Programme.

17. Natural Environment

Support preparation and promotion of Glasgow & Clyde Valley Forestry and Woodland Strategy

  • EDC
  • Clydeplan
  • Other Clydeplan Authorities

Glasgow & Clyde Valley Forestry and Woodland Strategy published in 2020

18. Water Environment and Flood Risk

Implement Surface Water Management Plans

  • EDC
  • SEPA
  • Scottish Water

Feasibility studies for all 3 SWMPs are completed and require to be developed in the next Flood Risk Management planning cycle (2). These will be dependent on

funding from COSLA and the Scottish Government.

Take forward the actions in the Climate Action Plan.

  • EDC

To be taken forward from 2024 onwards.

Continue to work with Metropolitan Glasgow Strategic Drainage Partnership (MGSDP) to produce projects in East Dunbartonshire

  • EDC
  • MGSDP

The Council is continuing to engage with the Partnership as part of wider city region workstreams including the forthcoming RSS.

 

Prepare and adopt Planning Guidance on the Water Environment

  • EDC

Public consultation September to October 2022

19. Historic Environment

Prepare and publish updated Historic Environment review,

including new Conservation Area Appraisals

  • EDC
  • Land Use Consultants

In progress. Updated Historic Environment

Planning Guidance to be produced.

20. Managing Waste

Monitor progress of Clyde Valley Residual Waste Project - Household waste recycling centre and waste transfer station at Mavis Valley, Bishopbriggs,

  • EDC
  • Clyde Valley Residual Waste Project team
  • The Project has signed a contract with Viridor Waste Management, over a 25 year period, starting on 1 December 2019.
  • The company will design, construct, finance and operate the facilities to treat waste which would otherwise go to landfill.
  • Waste will be transported to Viridor's treatment facility at Bargeddie, North Lanarkshire where recyclable material will be extracted and Refuse Derived Fuel produced

Monitor implementation of Waste Hierarchy as part of development management process

EDC

Ongoing

21. Mineral Resources

Promote responsible extraction of resources at Douglasmuir Quarry

  • EDC
  • Lafarge- Tarmac

(Quarry Operator)

  • Quarry in operation for sand and gravel
  • Restoration plan to be agreed once quarry ceases operations

Promote responsible extraction of resources at Inchbelle Quarry

  • EDC
  • Lafarge- Tarmac (Quarry Operator)
  • Quarry in operation for sand and gravel
  • Restoration plan to be agreed once quarry ceases operations
 

Ensure that the impacts of mineral extraction are properly addressed through restoration and enhancement.

  • EDC Lafarge- Tarmac (Quarry Operator)

No restoration or enhancement projects at present but will be monitored during the life of the plan,

22. Digital Communications

Liaise with private sector providers to help improve the digital communications infrastructure as a required element of new development allocations. This will be considered in site briefs. In addition, support the roll out

of the 5G network.

  • EDC
  • Digital Scotland,
  • Scottish Government

The Council is monitoring delivery of the Digital Planning aspect of the national Planning Reform agenda.

Monitor the delivery of broadband improvements within East Dunbartonshire.

  • EDC
  • Digital Scotland

Identifying opportunities for cabling that could be delivered alongside other infrastructure such as the electricity grid and

walking and cycling networks, including in site briefs.

  • Openreach
  • EDC

23. Airport and Hazardous Installations

Monitor Implementation of Policy 23 and consult on relevant applications through development management process.

  • EDC
  • Health and Safety Executive
  • Hazardous installations operators
  • Glasgow Airport

Ongoing. The Council is actively engaging with Glasgow Airport on the Airspace Change Programme including the recently concluded Design Principles stage and forthcoming Route Options stage.

24. Developer Contributions

Monitor implementation of policy 24 through development management process and establish methodology for recorded

usage

EDC

Ongoing

Produce Supplementary Planning Guidance on Developer Contributions to provide additional information and updates on health, education and any other relevant contributions as required.

EDC

Developer Contributions guidance published Sept 2022.