Introduction
Section 21 of the Planning etc. (Scotland) Act 2006 (“The Act”) requires planning authorities to prepare an Action Programme setting out how the authority proposes to implement their Local Development Plan (LDP). The Planning (Scotland) Act 2019 subsequently amended Section 21 so that Action Programmes are now known as Delivery Programmes. However, as the LDP2 has been prepared under the 2006 Act, it will continue to be referred to as an ‘Action Programme’. This Action Programme therefore accompanies the East Dunbartonshire Local Development Plan 2 in accordance with The Planning etc (Scotland) Act 2006. Under Planning Regulations, the finalised Action Programme must be adopted and published by the Council within three months of the adoption of the Local Development Plan 2.
On this page you will find information on:
- Section 1 - Development Strategy (Policy 1)
- Section 2 - Community Area
- Section 3 - Subject Policies (9-24)
Purpose
The Action Programme is intended to help align the delivery of the Local Development Plan 2 with corporate and national investment in infrastructure. It will be used by the Council as a delivery mechanism to deliver the best possible outcome for the area and to co-ordinate development proposals with the infrastructure and services needed to support them.
This Action Programme has the following purpose:
- It sets out a detailed plan of actions needed to deliver the key infrastructure, proposed development sites and policies set out in the Plan;
- It acts as a project management tool for coordinating the partnership working required to deliver the Plan by a range of organisations;
- It provides an understanding the likely costs of delivering the Plan and coordinating funding sources; and
- It is a mechanism for monitoring whether commitments are being met.
Specific site requirements and expectations are not repeated within this Action Programme. Instead, it focuses on the key actions that are required to deliver each site and implement each policy included within LDP2.
Understanding the Action Programme
Section 1 – Development Strategy – This section provides details of how the Council expects each individual aspect of the Development Strategy to be delivered.
Section 2 - Community Areas – The LDP 2 groups East Dunbartonshire into seven ‘community areas’ to reflect local geographies and community requirements. The Community Policy for each area provides a detailed development strategy and development priorities. This section of the Action Programme provides an overview of the key projects and infrastructure requirements within each area, together with a summary of how these are expected to be delivered. It also identifies local site specific designations, features and land use proposals or projects. The ‘progress’ column within these tables will be updated at each monitoring stage, where required.
Section 3 - Subject Policies – The Plan contains 16 ‘subject policies’ which will be used to assess planning applications. These are categorised into overall policies applicable to all applications, specific policies which relate to a certain land use or type of proposal, general safeguarding and protection policies which apply when a proposal has a particular site specific consideration or opportunity, and a policy setting out developer contribution requirements. This section of the Action Programme provides an overview of how these should be implemented. The ‘progress’ column within these tables will be updated at each monitoring stage, where required.
Delivery Partners
Collaboration between the private and public sectors is needed to deliver development, planned infrastructure and services throughout our communities. This will be supported by guidance and advice provided by key agencies and other regulatory organisations. Joint working and action between a wide range of partners will therefore be essential in delivering the spatial strategy, policies and proposals within the Plan. This includes landowners, developers, key agencies, community groups and other public sector organisations.
In some cases, developer contributions will be sought to achieve sustainable growth and development, as set out in Policy 24. In addition, the funding of many proposals contained within the Action Programme will be dependent on future Scottish Government spending reviews and the availability of public and private sector finance such as government infrastructure funding.
The Council will also work closely with our neighbouring authorities through the City Region, Clydeplan and other regional partners to ensure that opportunities for economic growth and the creation of sustainable patterns of development and infrastructure needs are planned for collaboratively across boundaries.
Monitoring
The delivery of sites and development can often be complex and in many cases subject to delay or slippage as a result of both internal and external factors. The Action Programme therefore needs to be flexible in response to change, proposing alternative solutions when needed (so long as these are consistent with the Development Plan) and assessing the impact of any change on remaining proposals. Governance arrangements will be put in place to ensure progress is sufficiently monitored and that actions are taken forward by the relevant organisations within a reasonable timescale.
The Council is required to review and republished the Action Programme at least every two years. This will allow the Council to provide updates on the progress of actions and review the format where required. On publication, it will be available on-line and copies will be sent to Scottish Ministers.
If you have and questions about this Action Programme, please contact the Land Planning Policy team by email at development.plan@eastdunbarton.gov.uk or by telephone via 0345 123 4510 (Customer Services).
Section 1 - Development Strategy (Policy 1)
The following table provides details of how the key elements of the development strategy will be delivered by the end of the LDP 2 period (2027).
Key Elements |
Action |
Responsibility / Delivery Partner(s) |
Progress |
---|---|---|---|
Direct development to brownfield sites in the urban area and the key areas of change |
Monitor vacant and derelict land annually |
EDC |
Ongoing. Data for 2021- 22 submitted to Scottish Government in September 2022. The Council is also working directly with the Glasgow City Region team to explore issues around remediation and the reduction in VDL sites in general. |
Prepare brownfield land strategy and planning guidance |
EDC |
Updated Brownfield Land Planning Guidance published September 2022. Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023. |
|
Develop allocated housing sites |
Engage with house builders and work proactively to bring forward and commit to the development of the sites that they have promoted for inclusion within the plan. |
Landowners and developers (further details contained within community area sections) EDC |
Sites agreed through examination and LDP2 published in November 2022. Work to deliver sites is ongoing. |
Key Elements |
Action |
Responsibility / Delivery Partner(s) |
Progress |
---|---|---|---|
Support the vitality and viability of town and village centres and the regeneration of the Place Plan areas |
Continue to implement adopted town centre strategies |
EDC, local businesses, community groups |
Significant progress has been made on all 3 TCSs. In Bearsden, accessibility enhancements are being taken forward via the Active Travel Strategy 2. Redevelopment of Brookwood Villa underway following successful funding bid. Due for completion in 2023. In Bishopbriggs, redevelopment of the former High School site is underway and work related to public realm enhancements as part of the City Deal Place and Growth Programme is ongoing. In Milngavie, a wide range of public realm and improvements to the business environment have already been achieved via the Milngavie BID team and local community groups. See relevant community area policies and Policy 14 for more information. |
Develop town centre strategy for Kirkintilloch |
EDC, local businesses, community groups |
A range of physical and non-physical initiatives continue to be developed and delivered under the existing town centre strategy for Kirkintilloch (The Kirkintilloch Town Centre Masterplan), also informed by more recent community lead engagement. – see Policy 4 for more information. |
Key Elements |
Action |
Responsibility / Delivery Partner(s) |
Progress |
|
---|---|---|---|---|
|
Promote and implement Local Place Plans Work with landowners to manage peatland for carbon mitigation and biodiversity, including Lenzie Moss, High and Low Moss, Campsie Fells and Barbeth Moss. Manage woodlands to encourage recreational access and biodiversity. Establish appropriate solutions to the problems associated with disused land, poor quality green space, upland areas and fragmented habitats, though the Glasgow and the Clyde Valley Green Network Partnership. |
EDC, community groups |
The Council is undertaking early preparatory work, including a revised Development Plan Scheme and Participation Statement, which will address the role of LPPs. Further engagement with local communities will take place in 2023. |
|
Protect, enhance and expand the green network |
|
Ongoing
|
||
|
Clydeplan Forestry and Woodland Strategy published in December 2020. The Council is also engaging with Scottish Forestry in relation to a Long Term Forest Plan for Lennox Forest. |
|||
developers
|
Ongoing
|
|||
|
||||
|
||||
Section 2 - Community Area
Policy 2 - Bearsden Community Area
Map – Council projects identified in the Bearsden Community Policy in LDP2 (Policy 2.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions & Delivery Requirements |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Bearsden Town Centre
|
|
EDC Local Traders Group and other businesses
|
2027
|
Town centre strategy in place (2018). Work towards enhanced accessibility via Active Travel Strategy 2 underway. Evidence base established and report due to be presented to Committee in Jan 2023. Redevelopment of Brookwood Villa underway following successful funding bid. Due for completion in 2023.
|
Site Name / Theme |
Actions & Delivery Requirements |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Local Centres (Baljaffray. Bearsden Station, Canniesburn, Kessington, Hillfoot) |
Protect function of all centres by ensuring adherence to sequential test approach |
EDC |
2027 |
The Council is maintaining strong protection of local centres via the development management process for relevant planning applications. |
2.BE1 Canniesburn Gate |
Continue to protect the role and function of this fully occupied site. |
Current occupiers |
2027 |
Ongoing |
2.BE2 Garscadden Depot |
Determination of planning permission |
Site developer |
2027 |
Site has been disposed and Council is awaiting planning application. |
2.BE3 Garscube Estate |
Establish potential for site use and/or intensification as part of future brownfield land strategy |
Glasgow City Council City Deal Project team Current occupiers |
2027 |
Wider site (West of Scotland Science Park, Glasgow) currently identified as a Strategic Economic Investment Location. |
Antonine Wall World Heritage Site |
Publish and promote updated Supplementary Guidance |
Antonine Wall Protection Group |
2023 |
Council is currently liaising with other member Councils on finalising the guidance ahead of publication. East Dunbartonshire Council consulted on the draft Guidance in 2022. |
Site Name / Theme |
Actions & Delivery Requirements |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
2.H1 Bearsden Golf Course |
Monitor development of site in line with planning consent |
Site developer |
2024 |
Under construction |
2.H2 Castlehill Farm |
Monitor development of site in line with planning consent |
Site developer |
2023 |
Under construction |
2.H3 Drymen Road |
None |
EDC Site developer |
2021 |
Complete |
2.H4 Crarae Avenue |
Engage with site owner to bring forward site. |
EDC Site developer |
2021 |
Engagement to take place as part of Housing Land Audit 2023. |
2.H5 Kilmardinny |
Engage with site owner/ developer and work proactively to bring forward the remaining development of the site. |
Site developer |
2022 |
Majority of site now complete. Only remaining area to the south remains undeveloped – expected to be delivered within lifespan of Plan. |
2.H6 190-196 Milngavie Road |
Engage with site owner/ developer and work proactively to bring forward the development of the site. |
Site developer |
2027 |
Land owner expects development to come forward later in plan period |
2.H7 Netherton Farm Lane |
Monitor site construction |
EDC Site developer |
2022 |
Under construction |
2.H8 Nithsdale Crescent |
Determination of planning permission |
EDC |
2022 |
A recent CPO by the Council was unsuccessful. The Council is now undertaking additional feasibility work with the aim of being in a position to determine alternative options by April 2023. |
Policy 3 - Bishopbriggs Community Area
Map – Council projects identified in the Bishopbriggs Community Policy in LDP2 (Policy 3.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Auchinairn Place Plan |
Support implementation of the Place Plan including:
|
EDC |
2024 |
Place Plan runs from 2019-2024. |
Bishopbriggs Town Centre |
|
EDC |
2027 |
The Council’s City Deal projects – the East Dunbartonshire Place and Growth Programme – will support the delivery of the town centre strategy. This includes a Public Realm Plan and development of the former Bishopbriggs High School Site. The Council also conducted a consultation on potential new business space in Spring 2022. |
Auchinairn Local Centre |
Protect function of centre by ensuring adherence to sequential test approach |
EDC |
2027 |
Ongoing |
Strathkelvin Retail Park |
|
EDC |
2027 |
Ongoing |
Westerhill Regeneration Area |
|
Site developers EDC |
2027 |
All aspects are ongoing as part of the City Deal Place and Growth Programme. |
3.BE2 Bishopbriggs Industrial Estate |
Establish potential for vacant site use and/or intensification |
EDC Site developers |
2027 |
Vacant and Derelict Land audit and storymap to be published early 2023. |
3.BE6 Low Moss Industrial Estate |
Monitor development of site in line with planning consent |
EDC Site developer |
2027 |
Under construction |
3.BE8 Westerhill Industrial Estate |
|
Site developers EDC |
2027 |
Ongoing as part of the City Deal Place and Growth Programme |
3.H1 Auchinairn Primary School, Former, Beech Road |
Submit planning application and progress through development management process |
Site developer EDC |
2026 |
Future action |
3.H2 Bishopbriggs Town Centre/ Former High School |
Monitor site construction |
Site developer EDC |
2027 |
Under construction |
3.H3 Cadder Sewage Works/Jellyhill |
Monitor site construction |
Site Developer EDC |
2024 |
Under construction |
3.H4 St Mungo Street |
None |
EDC |
2022 |
Complete |
3.H5 Westerhill Regeneration Area |
|
Site developers EDC |
2032 |
Ongoing as part of the City Deal Place and Growth Programme. |
3.BR1 Barrage Balloon Site |
Part of Westerhill Regeneration Area – see 3.H5 |
3.H5 |
2027 |
Ongoing as part of the City Deal Place and Growth Programme. |
3.BR3 Crofthead Quarry |
Establish green network enhancement opportunity for grassland, woodland Undertake ground Investigation due to former landfill use. |
EDC Site owner |
2027 |
Site is designated as a Green Network node and Open Space, LNCS and Habitat Link in LDP2. Value and potential of site will also be explored via Greenspace Strategy in 2023. |
3.BR4 Low Moss Industrial Estate |
See 3.BE6 |
|
2027 |
Under construction (data centre) |
3.BR5 Meadowburn, Former Quarry |
Establish green network enhancement opportunity – woodland and grassland. Undertake ground Investigation, due to former quarry use. |
2027 |
Site continues to be recorded on VDL register. Audit scheduled for publication late 2022. |
|
3.BR6 Westerhill Road, Former Oil Terminal |
See 3.H5 |
2027 |
Ongoing as part of the City Deal Place and Growth Programme. |
|
3.BR7 Westerhill Road South |
See 3.H5 |
2027 |
Ongoing as part of the City Deal Place and Growth Programme. |
Policy 4 - Kirkintilloch, Lenzie and Waterside Community Area
Map – Council projects identified in the Kirkintilloch, Lenzie and Waterside Community Policy in LDP2 (Policy 4.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Hillhead and Harestanes Place Plan |
Support implementation of projects identified |
Local Community EDC |
2023 |
Place Plan runs from 2018-2023 |
Kirkintilloch Town Centre |
|
|
2027 |
Delivery of the Kirkintilloch Town Centre Masterplan continues with The Council’s current activities focused on the redevelopment of Regent’s Gardens. Projects have been delivered by Kirkintilloch Community Council (Your Kirky) such as the Townhead Square project. The development of a town centre strategy for Kirkintilloch will be considered with the community as part of developing LDP3. |
Local Centres (Lenzie, Merkland and Millersneuk) |
Protect function of centre by ensuring adherence to sequential test approach |
EDC |
2027 |
Ongoing |
4.BE5 Kirkintilloch Industrial Estate East |
Establish potential for vacant site use and/or intensification as part of future brownfield land strategy |
EDC Site developers |
2027 |
Ongoing |
4.BE6 Milton Road |
Establish potential for vacant site use as part of future brownfield land strategy |
EDC Site developers |
2027 |
Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023. |
4.BE7 Pit Road |
Establish feasibility of improving access to site and overall condition of site |
EDC Site owners |
2027 |
To be undertaken within lifespan of the Plan |
4.BE10 Southbank Works |
Establish potential for vacant site use as part of future brownfield land strategy |
EDC Site developers |
2027 |
Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023. |
4.BE11 Woodilee Industrial Estate |
Establish potential for vacant site use as part of future masterplan |
EDC Site developers |
2027 |
The Masterplan was completed in 2022. Planning consents are now being brought forward on the site |
4.H1 Armour Drive Lock Ups |
None |
EDC |
2021 |
Complete |
4.H2 Blackthorn Grove Lock Ups (Lenzie) |
None |
EDC |
2021 |
Complete |
4. H3 Braes O'Yetts |
None |
Site developer |
2022 |
Complete |
4.H4 Broomhill Hospital |
Monitor site construction |
Site developer EDC |
2024 |
Under construction |
4.H5 Campsie View School |
Submit planning application |
Site developer/EDC |
2032 |
Future action |
4.H6 Claddens South/ Blackland Place |
Monitor site construction |
Site developer EDC |
2022 |
Under construction |
4.H7 Cleddans Playing Field |
Submit refreshed planning application |
EDC |
2023 |
Future action |
4.H8 David Gray Drive/ Fossil Grove |
None |
EDC |
2027 |
Complete |
4.H9 Duntiblae |
Engage with site owner/ developer and work proactively to bring forward the development of the site. |
Site developer EDC |
2025 |
Future action |
4.H10 Fauldhead/ Chryston Road North |
Conclude legal agreement and fulfil pre-start conditions. |
Site developer EDC |
2025 |
Planning application granted subject to conclusion of legal agreement |
4.H11 Fauldhead/Chryston Road South |
Conclude legal agreement and fulfil pre-start conditions. |
Site developer EDC |
2025 |
Planning application granted subject to conclusion of legal agreement |
4.H12 Glasgow Rd |
Submit planning application |
EDC |
2023 |
Future action |
4.H13 High Street/ Mitchell Hire |
Monitor site construction |
Site developer EDC |
2022 |
Under construction |
4.H14 38 Kilsyth Road |
None
|
RSL |
2023 |
Complete |
4.H15 Kirkintilloch Gateway Regeneration Area |
Engage with site owner/ developer and work proactively to bring forward and commit to the development of the site as part of masterplan. |
Site owners EDC |
2032 |
The Masterplan was completed in 2022. Planning consents are now being brought forward on the site. |
4.H16 Lairdsland School |
Monitor site construction |
EDC |
2022 |
Under construction, completion anticipated March 2023 |
4,H17 Lenzie Primary, former |
Monitor site construction |
Site developer EDC |
2021 |
Under construction |
4.H18 Meadowburn Avenue |
Engage with site owner/ developer and work proactively to bring forward the site. |
Site developer EDC |
2027 |
Ongoing |
4.H19 Merkland School |
Submit planning application |
Site Developer/EDC |
2032 |
Ongoing |
4.H20 Moss Road |
Submit planning application |
EDC |
2027 |
Ongoing |
4.H21 Redbrae Road/ Oxgang Holdings |
Conclude renegotiated legal agreement and recommence works on site |
Site developer EDC |
2022 |
Ongoing legal procedures due to liquidation of previous developer |
4.H22 Rob Roy Football Club Phase 2 |
Monitor site construction |
Site developer |
2023 |
Under construction, completion anticipated Jan 2023 |
4.H23 St Agatha’s Primary, former |
Monitor site construction |
EDC |
2022 |
Complete |
4.H24 Tom Johnston House, former |
None |
EDC |
2022 |
Complete |
4.H25 Townhead (85 – 97) |
None |
RSL |
2021 |
Complete |
4.H26 Whitegates |
Monitor site construction |
Site developer EDC |
2027 |
Under construction |
4.BR9 Waterside Bing |
Engage with site owner and work proactively to bring forward required site use (biodiversity green network enhancements) |
EDC Landowner |
2027 |
Further action |
Policy 5 - Lennoxtown, Milton of Campsie, Haughhead and Clachan of Campsie Community Area
Map – Council projects identified in the Lennoxtown, Milton of Campsie, Haughhead and Clachan of Campsie Community Policy in LDP2 (Policy 5.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions |
Responsibility/Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Lennoxtown Place Plan |
|
EDC Community groups |
2023 |
Currently being implemented. |
|
|
|
Lennoxtown Streetscene Project concept design refresh started for completion by end 22/23. Public consultation underway. |
|
Lennoxtown Village Centre |
Protect function of centre by ensuring adherence to sequential test approach |
EDC |
2027 |
Ongoing |
Milton of Campsie Village Centre |
Protect function of centre by ensuring adherence to sequential test approach |
EDC |
2027 |
Ongoing |
Lennoxtown Enterprise Centre |
Market vacant units for office or appropriate employment use |
EDC |
2027 |
Ongoing |
5.H1 Baldoran House |
None |
EDC |
2021 |
Complete |
5.H2 Birdston Road |
None |
EDC |
2022 |
Complete |
5.H3 Campsie Golf Club, Lennoxtown |
Engage with site owner/ developer and work proactively to bring forward the site. |
Site developer EDC |
2027 |
Future action |
5.H4 East of Aldessan House |
Monitor site construction |
Site developer EDC |
2025 |
Ongoing |
5.H5 Lennox Castle Hospital |
Engage with site owner/ developer and work proactively to bring forward the site. |
Site developer EDC |
2027 |
Future action |
5.H6 Lennoxlea, Lennoxtown |
Engage with site owner/ developer and work proactively to bring forward the site. |
Site developer EDC |
2027 |
Future action |
5.H7 Primrose Way |
|
EDC |
2027 |
Future action |
5.H8 St Machan’s Way, Lennoxtown |
Submit planning application |
EDC |
2027 |
Future action |
5.H9 Watshod Farm |
None |
Site developer |
2021 |
Complete |
Main Street |
Establish opportunities for biodiversity enhancement and green network improvements |
EDC |
2027 |
Lennoxtown Streetscene Project underway. |
5.BR1 Lennox Castle |
Engage with site owner and work proactively to bring forward and commit to the development of the site for a suitable use. |
EDC Site Owner |
2027 |
Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023. |
5.BR2 Lennox Castle Hospital |
See 5.H5 |
2032 |
See 5.H5 |
|
5.BR3 Main Street (rear of properties) |
Engage with landowner to take forward required site uses (biodiversity) |
Landowner EDC |
2027 |
Analysis of individual sites including ownership status is also underway and a more detailed audit/ storymap is due to be published in early 2023. |
Policy 6 - Milngavie Community Area
Map – Council projects identified in the Milngavie Community Policy in LDP2 (Policy 6.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Milngavie Town Centre |
|
|
2027 |
Ongoing. The Council is continuing to engage with and support Milngavie BID on delivering the business plan and in delivering the Town Centre Strategy. Public realm improvements delivered 2021 by Milngavie BID. |
6.BE1 Cloberfield |
|
EDC Site owner |
2027 |
There are a small number of vacant sites within the industrial estate and these are being recorded via the annual vacant and derelict land survey. Detailed VDL audit is due to be published in 2023. |
6.H1 Bankell Farm |
None |
Site developer |
2021 |
Complete |
6.H2 Craigton Rd |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2025 |
Ongoing |
6.H3 Drumclog Ave |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2027 |
Ongoing |
6.H4 Keystone Road |
None |
EDC |
2021 |
Complete |
6.H5 Fire Station Field |
None |
Site developer |
2022 |
Complete |
6.H6 No 18 Strathblane Rd |
Fulfil pre-start conditions. |
Site developer EDC |
2025 |
Planning consent granted on appeal |
6.BR3 Craigton Works |
Engage with site owner/ developer and work proactively to bring forward and commit to the development of the site. |
Site developer |
2027 |
Ongoing |
Policy 7 - Torrance and Baldernock Community Area
Map – Council projects identified in the Torrance and Baldernock Community Policy in LDP2 (Policy 7.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress (note: column to be completed and updated prior to final publication) |
---|---|---|---|---|
Torrance Village Centre |
Protect function of centre by ensuring adherence to sequential test approach |
EDC |
2027 |
Ongoing |
7.H1 Acre Valley Nursery |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2027 |
Ongoing |
7.H2 Balmore Garden Nursery |
Determine planning application |
Site developer EDC |
2023 |
Planning application under consideration |
7.H3 East of Ferrymill Motors |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2027 |
Ongoing |
7.H4 Kelvindale Nursery |
Submit planning application |
EDC |
2027 |
Future action |
7.H5 Kelvin View |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer RSL EDC |
2023 |
Ongoing |
7.H6 Main Street (North) |
None |
EDC |
2020 |
Complete |
7.H7 Main Street (South) |
Submit planning application |
EDC |
2025 |
Future action |
Policy 8 - Twechar Community Area
Map – Council projects identified in the Twechar Community Policy in LDP2 (Policy 8.CF)
Table – Other key sites and proposed developments identified in LDP2
Site Name / Theme |
Actions |
Responsibility/ Delivery Partner(s) |
Target Delivery Date |
Progress |
---|---|---|---|---|
Twechar village centre |
Protect function of centre by ensuring adherence to sequential test approach |
EDC |
2027 |
Ongoing |
Twechar Place Plan |
Support implementation of projects identified |
EDC Local Community |
2023 |
Place Plan runs from 2018-2023 |
8.BE1 Badenheath |
Engage with site owner/ developer and work proactively to bring forward development of the site. Undertake the following as a minimum:
|
Site developer EDC |
2027 |
Ongoing |
8.H1 Canalside (Barrhill Lodge and 1 Glen Shirva Rd) |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2027 |
Ongoing |
8.H2 Glen Shirva Rd Main Site |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2027 |
Ongoing |
8.H3 MacDonald Crescent |
Engage with site owner/ developer and work proactively to bring forward development of the site. |
Site developer EDC |
2032 |
Ongoing |
8.BR2 Former Cemex Site (now Breedon) |
Establish potential for vacant site use |
EDC Site Owner |
2027 |
Site is being evaluated as part of the VDL annual survey 2022-23. |
Section 3 - Subject Policies (9-24)
Policy Name |
Actions |
Responsibility/ Delivery Partner(s) |
Timescales & Progress |
---|---|---|---|
9. Climate Change, Sustainability and Energy Infrastructure |
Prepare and publish EDC Climate Action Plan |
EDC |
In progress, completion expected 2023 |
Prepare and publish Local Heat and Energy Efficiency Strategy (LHEES) |
EDC |
In progress, completion expected 2023 |
|
Monitor use and implementation of Sustainability & Energy Statement Form as part of development management process |
EDC |
Ongoing |
|
10. Design and Placemaking |
Review current Supplementary Guidance and update to reflect new sustainability standards and any other requirements. |
EDC |
Complete (August 2022) |
Monitor implementation of Policy 10 through development management process |
EDC |
Ongoing |
|
11. Transport |
Prepare and publish Sustainable Transport Planning Guidance |
EDC |
Complete (August 2022) |
Deliver electric vehicle charging infrastructure in line with Electric Vehicle Action Plan |
EDC |
Ongoing |
|
Monitor air quality in Air Quality Management Areas in line with Local Air Quality Management obligations |
EDC |
Ongoing |
|
12. Housing |
Undertake Housing Land Audit annually to ensure an effective 5 year supply is maintained |
EDC |
Ongoing |
Monitor use of Policy 12 through development management process |
EDC |
Ongoing |
|
13. Community Facilities and Open Space |
Progress East Dunbartonshire Council Major Projects |
EDC |
Ongoing |
Publish new Open Space Strategy |
EDC |
In progress, completion expected in 2023 |
|
14. Network of Centres and Retailing |
Ensure implement town centre first principle to all relevant applications |
EDC |
Ongoing |
Monitor activity and occupancy at Strathkelvin Retail Park |
EDC |
Ongoing |
|
15. Business and Employment |
Deliver Economic Development Strategy and Produce Circular Economy Strategy |
EDC and EDEP |
In progress. Economic Recovery Plan published 2021. |
16. Tourism |
Encourage development of the visitor economy in line with Economic Development Strategy |
EDC and EDEP |
TBC |
Deliver Economic Development Strategy |
EDC and EDEP |
Economic Recovery Plan published 2021. Delivery is ongoing with a number of actions being completed and underway. Those relevant to LDP2 such as projects in the Community section of the ERP have progress noted in this Action Programme. |
|
17. Natural Environment |
Support preparation and promotion of Glasgow & Clyde Valley Forestry and Woodland Strategy |
|
Glasgow & Clyde Valley Forestry and Woodland Strategy published in 2020 |
18. Water Environment and Flood Risk |
Implement Surface Water Management Plans |
|
Feasibility studies for all 3 SWMPs are completed and require to be developed in the next Flood Risk Management planning cycle (2). These will be dependent on funding from COSLA and the Scottish Government. |
Take forward the actions in the Climate Action Plan. |
|
To be taken forward from 2024 onwards. |
|
Continue to work with Metropolitan Glasgow Strategic Drainage Partnership (MGSDP) to produce projects in East Dunbartonshire |
|
The Council is continuing to engage with the Partnership as part of wider city region workstreams including the forthcoming RSS. |
|
Prepare and adopt Planning Guidance on the Water Environment |
|
Public consultation September to October 2022 |
|
19. Historic Environment |
Prepare and publish updated Historic Environment review, including new Conservation Area Appraisals |
|
In progress. Updated Historic Environment Planning Guidance to be produced. |
20. Managing Waste |
Monitor progress of Clyde Valley Residual Waste Project - Household waste recycling centre and waste transfer station at Mavis Valley, Bishopbriggs, |
|
|
Monitor implementation of Waste Hierarchy as part of development management process |
EDC |
Ongoing |
|
21. Mineral Resources |
Promote responsible extraction of resources at Douglasmuir Quarry |
(Quarry Operator) |
|
Promote responsible extraction of resources at Inchbelle Quarry |
|
|
|
Ensure that the impacts of mineral extraction are properly addressed through restoration and enhancement. |
|
No restoration or enhancement projects at present but will be monitored during the life of the plan, |
|
22. Digital Communications |
Liaise with private sector providers to help improve the digital communications infrastructure as a required element of new development allocations. This will be considered in site briefs. In addition, support the roll out of the 5G network. |
|
The Council is monitoring delivery of the Digital Planning aspect of the national Planning Reform agenda. |
Monitor the delivery of broadband improvements within East Dunbartonshire. |
|
||
Identifying opportunities for cabling that could be delivered alongside other infrastructure such as the electricity grid and walking and cycling networks, including in site briefs. |
|
||
23. Airport and Hazardous Installations |
Monitor Implementation of Policy 23 and consult on relevant applications through development management process. |
|
Ongoing. The Council is actively engaging with Glasgow Airport on the Airspace Change Programme including the recently concluded Design Principles stage and forthcoming Route Options stage. |
24. Developer Contributions |
Monitor implementation of policy 24 through development management process and establish methodology for recorded usage |
EDC |
Ongoing |
Produce Supplementary Planning Guidance on Developer Contributions to provide additional information and updates on health, education and any other relevant contributions as required. |
EDC |
Developer Contributions guidance published Sept 2022. |